BLD-Final | 10/31/2016 | 10/31/2016 | 10/31/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
DOC - Permit Finaled | 10/31/2016 | 10/31/2016 | 10/31/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Framing/Rough-in | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Framing/Rough-in | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart. Floor joist hanger missing nails at top of stairs, Truss bracing f01g, header over window 2nd floor. ok to insulate
|
BLD-Wall Bracing | 8/4/2016 | 8/4/2016 | 8/4/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Wall Bracing | 8/4/2016 | 8/4/2016 | 8/4/2016 | A | FAIL |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Wall Bracing | 8/2/2016 | 8/2/2016 | 8/2/2016 | A | FAIL |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
Issue PAID IN FULL permit | | | 4/25/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 4/13/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 2/29/2016 | 2/29/2016 | 4/13/2016 | | DONE |
Brian McGowan
|
|
|
due 3/14 L2 Townhouse FAILED 3-08-16 - Fire wall discrepancy at end unit.
|
Routing - PLAN CHECK | 4/13/2016 | | 4/13/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 4/13/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/13/2016 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Bld | | | 4/13/2016 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2016 | | DONE |
|
|
|
called Leonard to let know permits are ready and how much is owed-left message on phone
|
Plan resubmittals received | | | 3/21/2016 | | DONE |
|
|
|
received 2 copies of sheets 2.0, 4.0, and 5.0- put with plans on Brian's desk
|
1st review completed | | | 3/8/2016 | | FAIL |
Brian McGowan
|
|
|
Fire wall discrepancy at end unit.
|
Routing - PLAN CHECK | 2/29/2016 | | 3/8/2016 | | FAIL |
Brian McGowan
|
|
|
Fire wall discrepancy at end unit.
|
Routing - MECHANICAL | 2/24/2016 | | 2/29/2016 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 2/22/2016 | | 2/29/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 2/23/2016 | | 2/24/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 2/22/2016 | | 2/23/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 2/22/2016 | | 2/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/22/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/22/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/22/2016 | | DONE |
|
|
|
|
Application received | | 2/22/2016 | | | |
|
|
|
|