Letter of compliance/Occupancy | | | 12/9/2016 | | DONE |
|
|
|
|
BLD-Final | 12/8/2016 | 12/8/2016 | 12/8/2016 | P | PASS |
Phil Shearer
|
|
|
access 3283 Phone #: ###-#### Inspection requested via web by David Wipper
|
DOC - Permit Finaled | 12/8/2016 | 12/8/2016 | 12/8/2016 | P | PASS |
Phil Shearer
|
|
|
|
PubWorks Occupancy Approval | 12/6/2016 | 12/6/2016 | 12/6/2016 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Aging Inspection | 11/2/2016 | 11/2/2016 | 11/7/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Other | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | DONE |
Tony Young
|
|
|
soffit
|
BLD-Other | 7/18/2016 | 7/19/2016 | 7/19/2016 | P | PASS |
Phil Shearer
|
|
|
soffit & fascia - Brandon Phone #: ###-####
|
BLD-Energy code compliance | 6/17/2016 | 6/20/2016 | 6/20/2016 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Wall Bracing | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | PASS |
Jim Sly
|
|
|
Larry Phone #: ###-####
|
BLD-Footing | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PASS |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | PEND |
Tony Young
|
|
|
Chris Phone #: ###-####,, needs soil report to public works for approval
|
BLD-Footing | 4/13/2016 | 4/13/2016 | 4/14/2016 | P | PEND |
Tony Young
|
|
|
Chris Phone #: ###-####
|
Routing PW Grading-Hillside | 4/14/2016 | | 4/14/2016 | | PASS |
Jim Wyllie
|
|
|
Received letter from geotechnical engineer approving footing subgrade. Okay to schedule a footing inspection.
Jim Wyllie / ###-####
|
Issue PAID IN FULL permit | | | 4/11/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/11/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 4/8/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 3/11/2016 | 3/11/2016 | 4/8/2016 | | DONE |
Brian McGowan
|
|
|
due 3/30 L2 hillside. Failed. Structure over Entry needed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/8/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLAN CHECK | 4/7/2016 | | 4/7/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 4/7/2016 | | 4/7/2016 | | PASS |
Celine Acord
|
|
|
|
Routing - PLANNING | 3/9/2016 | | 3/31/2016 | | PASS |
Sue Cummings
|
|
|
Has recorded easement for driveway access. See Documents
|
Routing - PLAN CHECK | 3/9/2016 | | 3/30/2016 | | FAIL |
Brian McGowan
|
|
|
Need structure and details over Main Entry.
Top Of foundation wall and footing need to be called out.
|
1st review completed | | | 3/30/2016 | | FAIL |
Brian McGowan
|
|
|
Need structure and details over Main Entry.
Top Of foundation wall and footing need to be called out.
|
Routing - Erosion and Sediment | 3/9/2016 | | 3/14/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Permit for the construction of a new 3103 sq. ft., one story single family dwelling with 5 bedrooms, 2.5 bathrooms, approximately *** sq. ft. of covered patio/porch and a 807 sq. ft. attached garage
|
Plan assigned to (LEG) Tisha | 3/9/2016 | | 3/11/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 3/9/2016 | | 3/11/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - FIRE | 3/9/2016 | 3/9/2016 | 3/9/2016 | | PASS |
Katie Marron
|
|
|
This structure has been evaluated for Fire department vehicle access. Addionally, the exterior of this structure is required to comply with the 30 foot Defensible Space provisions of the Boise Municipal Code 7-01-69 section 4920.
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/9/2016 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/9/2016 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 3/9/2016 | | 3/9/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 3/9/2016 | | 3/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/9/2016 | | 3/9/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 2/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 23 2016 3:12PM
|