BLD-Final | 5/22/2017 | 5/23/2017 | 5/23/2017 | P | PASS |
Dave Hannah
|
|
|
Rader Phone #: ###-####
|
DOC - Permit Finaled | 5/23/2017 | 5/23/2017 | 5/23/2017 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 5/18/2017 | 5/18/2017 | 5/18/2017 | | PASS |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | PASS |
Dave Hannah
|
|
|
Rader Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | PASS |
Dave Hannah
|
|
|
Call half hour before // Radier Phone #: ###-####
|
Plan Modification Accepted | | | 3/3/2017 | | DONE |
|
|
|
Revised manual J
|
Routing - MECHANICAL | 3/3/2017 | | 3/3/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Plan Modification Accepted | | | 2/21/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 2/21/2017 | | 2/21/2017 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Wall Bracing | 1/18/2017 | 1/18/2017 | 1/18/2017 | P | PASS |
Dave Hannah
|
|
|
Shear // Jeff Phone #: ###-####
|
Plan assigned to (BJM) | 11/3/2016 | 11/3/2016 | 12/16/2016 | | CANC |
Brian McGowan
|
|
|
Fail - Need clarification on floor structure, engineering for front entry roof, structure at rear entrance roof.
Tisha finished the review
|
BLD-Footing | 12/7/2016 | 12/7/2016 | 12/7/2016 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 12/7/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/7/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 12/6/2016 | | |
|
|
|
|
Telephone call | | | 12/6/2016 | | DONE |
|
|
|
Spoke with Jeff informing him that the plan mod is ready to be picked up and the fee amount due
|
Routing - PLAN CHECK | 11/28/2016 | | 12/6/2016 | | PASS |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/6/2016 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Routing - MECHANICAL | 12/5/2016 | | 12/5/2016 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (BLD) | 11/29/2016 | 11/29/2016 | 11/29/2016 | A | FAIL |
Tisha Gallop
|
|
|
discussed status of permit. Need mechanial and plan check approvals.
|
Routing Walk-In (BLD) | 10/27/2016 | 10/27/2016 | 11/29/2016 | A | DONE |
Brittany Hill
|
|
|
project will need further review - NOT a walk-in
|
Routing - MECHANICAL | 11/21/2016 | | 11/28/2016 | | FAIL |
Troy James
|
|
|
Emailed corrections to TML
|
Plan resubmittals received | | | 11/21/2016 | | DONE |
|
|
|
received Manual J- gave to Troy
|
Routing - MECHANICAL | 11/17/2016 | | 11/18/2016 | | FAIL |
Chad Schwendiman
|
|
|
Emailed correction to TML
|
Plan resubmittals received | | | 11/15/2016 | | DONE |
|
|
|
resubmittals received 2 sets of sheets A4.2, S1.0, SZ1.1, S1.2, S1.3, S2.0, 1 set of engineering cals, ICC report & letter from CoreEng-gave to Brian McGowan
|
Routing - PLAN CHECK | 11/3/2016 | | 11/9/2016 | | FAIL |
Brian McGowan
|
|
|
Need clarification on floor structure, engineering for front entry roof, structure at rear entrance roof.
|
1st review completed | | | 11/9/2016 | | FAIL |
Brian McGowan
|
|
|
Need clarification on floor structure, engineering for front entry roof, structure at rear entrance roof.
|
Routing Walk-In (Zoning) | 10/27/2016 | 10/27/2016 | 10/27/2016 | A | PASS |
Josh Wilson
|
|
|
Ok per DRH16-00103 and CVA16-00027. JGW
|
Plan Modification Accepted | | | 10/27/2016 | | DONE |
|
|
|
phase 2 of project-resubmitted 2 sets of A1.0, A1.1, A1.2, A1.3, A1.4, A2.0, A2.1, A2.2, A2.3, A3.0, A3.1, A4.0, A4.1, A4.2, A4.3, S1.0, S1.1, S1.2, S1.3, S2.0, S3.0, G1.0, G1.1, E1.0, E1.1, E2.0, E2.1, M1.1, P1.1-1 permit app, checklist, GC form, 4 P & Z letter, rescheck, manuals j, struc calcs-took to Brian McGowan
|
Routing Walk-In (BLD) | 2/25/2016 | 2/25/2016 | 2/25/2016 | A | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 2/25/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 2/25/2016 | | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 2/25/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 2/25/2016 | | 2/25/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/25/2016 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 2/25/2016 | | DONE |
|
|
|
|
Application received | | 2/25/2016 | | | |
|
|
|
|