Second Notice | | 10/20/2016 | 11/14/2016 | | DONE |
|
|
|
Mailed 11-16-16 (no trade values) This permit finaled on the web by Cameron Murphy
|
First Notice | | 9/30/2016 | 10/10/2016 | | DONE |
|
|
|
mailed 10-11-16
|
Temporary Occupancy | 9/20/2016 | 12/19/2016 | 9/20/2016 | | DONE |
Candy A. Nichols
|
|
|
Temp C of O for 175,990 sq ft-3 phases BLD15-04516, BLD15-04239 & BLD16-00605
|
Telephone call | | | 9/20/2016 | | DONE |
|
|
|
as per Ron Hill-1 c of o for 3 phases-BLD16-00605, BLD15-04516 & BLD15-04239
|
Permanent Occupancy | | | 9/20/2016 | | DONE |
|
|
|
3 phases are included in this C of O-see BLD15-04329 & BLD 15-04516 as well as BLD16-00605
|
Permanent Occupancy | | | 9/20/2016 | | DONE |
|
|
|
|
BLD-Final | 9/16/2016 | 9/19/2016 | 9/19/2016 | P | PASS |
Jim Storey
|
|
|
Rod Phone #: ###-####
|
FIRE-Final Inspection | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags, final life fire safety inspection for racking permit complete (BLD16-01910). Final life fire safety inspection passed/complete.
|
Zoning Approval | 9/14/2016 | 9/14/2016 | 9/14/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 6/8/2016 | 6/9/2016 | 6/9/2016 | P | PASS |
Jim Storey
|
|
|
Odie Phone #: ###-####
|
Print Occupancy Form | | | 4/8/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/5/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/5/2016 | | DONE |
|
|
|
|
Telephone call | | | 3/31/2016 | | DONE |
|
|
|
emailed Cameron Murphy the fees due
|
Plan assigned to (CDM) | 3/1/2016 | 3/1/2016 | 3/21/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 3/1/2016 | | 3/21/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 3/21/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/21/2016 | | DONE |
|
|
|
***requirements met***NEED GC form, Certificate of value from GC, and RP
|
Routing - Design Review | 3/10/2016 | | 3/10/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing - FIRE | 3/1/2016 | 3/1/2016 | 3/8/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PLUMBING | 3/1/2016 | | 3/2/2016 | | PASS |
Daryl Spivey
|
|
|
the only plumbing in this phase is capping a sink waste.
|
Routing - Addressing | 3/1/2016 | | 3/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/1/2016 | | 3/1/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 3/1/2016 | | 3/1/2016 | | FAIL |
Andrea Tuning
|
|
|
Appeal period does not expire until Thursday March 10, 2016.
|
Intake Approval | | | 3/1/2016 | | PASS |
|
|
|
|
Pending Assignment by TLW | 3/1/2016 | | 3/1/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 2/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 29 2016 8:23AM
|