First Notice | | 9/17/2016 | 10/18/2016 | | DONE |
|
|
|
Mailed 10-18-16
|
Meeting | | | 9/7/2016 | | DONE |
|
|
|
general contractor states that the only mechanical work done was moving thermostats. as per phone call with Bill Vandegrift, Bill mentioned that there were (2) conference rooms that did NOT show ventilation/ducting for air conditioning on the plans.
|
Permanent Occupancy | | | 9/7/2016 | | DONE |
|
|
|
|
BLD-Final | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Dave Hannah
|
|
|
Larren Phone #: ###-####
|
BLD-Final | 6/30/2016 | 6/30/2016 | 7/12/2016 | P | FAIL |
Dave Hannah
|
|
|
Larren-see docuiments for letter on temp glass-mech not signed off so if not needed can you please sign off on the card Phone #: ###-####
|
BLD-Final | 6/27/2016 | 6/27/2016 | 6/28/2016 | P | PEND |
Dave Hannah
|
|
|
Larren Phone #: ###-#### temp glassing
|
BLD-Final | 6/2/2016 | 6/6/2016 | 6/7/2016 | P | PART |
Dave Hannah
|
|
|
Larren Phone #: ###-#### ok for temp needs to install conf rm glassing
|
FIRE-Final Inspection | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguisher is in place with current inspection tag. Final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 6/2/2016 | 6/3/2016 | 6/3/2016 | A | CANC |
Jim Page
|
|
|
Contacted Larren Phone #: ###-#### for final life fire safety inspection, area of work still has a FIR permit for fire alarms in issued status, cannot complete life fire safety inspection until FIR permit for fire alarms has benn inspected/ has been finaled. This inspection request cancelled.
|
BLD-Framing/Rough-in | 4/25/2016 | 4/25/2016 | 4/26/2016 | P | PASS |
Dave Hannah
|
|
|
Larren Phone #: ###-####
|
BLD-Framing/Rough-in | 4/22/2016 | 4/22/2016 | 4/24/2016 | P | DONE |
Dave Hannah
|
|
|
Larren Phone #: ###-####
|
BLD-Framing/Rough-in | 4/21/2016 | 4/22/2016 | 4/23/2016 | A | PEND |
Dave Hannah
|
|
|
Larren Phone #: ###-#### needs to remove screws fro top track that are in grid
|
Issue PAID IN FULL permit | | | 4/21/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/21/2016 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 3/14/2016 | 3/14/2016 | 3/28/2016 | | PASS |
Carl D Madsen
|
|
|
Level II, 12th floor US Bank Bldg
|
Routing - PLAN CHECK | 3/14/2016 | | 3/28/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 3/28/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2016 | | DONE |
|
|
|
Need Revised Cert of Value and **MET** GC Form
|
Routing - Addressing | 3/14/2016 | | 3/15/2016 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 3/14/2016 | | PASS |
David Ferguson
|
|
|
|
Routing - PUBLIC WORKS | 3/14/2016 | | 3/14/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 3/11/2016 | | FAIL |
David Ferguson
|
|
|
Need #518 - Minor Tenant Improvement Submittal Checklist submitted.
|
Application received | | | 2/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 29 2016 10:18AM
|