Second Notice | | 10/22/2017 | 10/17/2017 | | DONE |
|
|
|
This permit finaled on the web by Andrew Stewart
|
First Notice | | 9/21/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
Permanent Occupancy | | | 9/11/2017 | | DONE |
|
|
|
|
BLD-Final | 9/7/2017 | 9/8/2017 | 9/8/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brad Turk. All issues resolved. Ok for perm occ.
|
FIRE-Final Inspection | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Project related fire alarm permit complete.
|
BLD-Framing/Rough-in | 3/10/2017 | 3/13/2017 | 3/10/2017 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Final | 11/17/2016 | 11/17/2016 | 11/17/2016 | A | PEND |
Jim Sly
|
|
|
Brad Turk Phone #: ###-#### Inspection requested via web by Brad Turk Waiting for Contractor to resolve alarm issues.
|
BLD-Conference | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Mike Jordan
|
|
|
Brad Turk Phone #: ###-#### Inspection requested via web by Brad Turk. Ok for temp occ. Verify tempered glazing in doors and provide ADA compliant hardware at egress path.
|
FIRE-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy for life safety is ok per Scott for 30 days so that the project related fire alarm permit can be addressed.
|
FIRE-Final Inspection | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | FAIL |
Troy Cobbley
|
|
|
Life safety is ok but is being held up by issues with the project related fire alarm permit.
|
BLD-Ceiling Grid Inspection | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | PASS |
Mike Jordan
|
|
|
Brad Turk Phone #: ###-#### Inspection requested via web by Brad Turk
|
BLD-Framing/Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PASS |
Mike Jordan
|
|
|
Brad Turk Phone #: ###-#### Inspection requested via web by Brad Turk
|
BLD-Framing/Rough-in | 7/15/2016 | 7/18/2016 | 7/18/2016 | A | PART |
Jim Storey
|
|
|
As early as you can. See...Brad Turk Phone #: ###-#### Inspection requested via web by Brad Turk ok to gyp all but smoke partition behind ramp wall and three floor drain that need fire stopping.
|
BLD-Framing/Rough-in | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | DEFR |
Phil Shearer
|
|
|
Out of time
|
Issue PAID IN FULL permit | | | 7/15/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/15/2016 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/1/2016 | 4/1/2016 | 6/13/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) SARMC "EASY STREET" - (Apr 19 - 15 days) - Level 3 TI - ePlanReview
|
Routing - PLAN CHECK | 6/10/2016 | | 6/13/2016 | | PASS |
Carl Westfall
|
|
|
Drawings approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/13/2016 | | DONE |
|
|
|
***MET*** NEED GC and certificate of value
|
Plan resubmittals received | | | 6/10/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/8/2016 | | 6/9/2016 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Plan resubmittals requested | | | 6/9/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/8/2016 | | DONE |
Carl Westfall
|
|
|
|
1st review completed | | | 4/26/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/26/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/1/2016 | | 4/26/2016 | | FAIL |
Carl Westfall
|
|
|
|
Routing - FIRE | 4/1/2016 | 4/1/2016 | 4/8/2016 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 4/1/2016 | | 4/6/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 4/1/2016 | | 4/4/2016 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 4/1/2016 | | 4/4/2016 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 4/1/2016 | | 4/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Pending Assignment by JCB | 4/1/2016 | | 4/1/2016 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 3/30/2016 | | FAIL |
David Ferguson
|
|
|
It appears from your plumbing plan that you are proposing to saw cut over 40 lineal feet of concrete. This will require a Erosion & Sediment Control Waiver letter. Please provide a letter stating how the project manager is to dispense and store the removed concrete.
|
Intake Approval | | | 3/30/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Dave Ferguson and plan review fees paid.
|
Application received | | | 3/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 1 2016 9:03AM
|