BLD-Final | 12/21/2016 | 12/22/2016 | 12/22/2016 | A | PASS |
Tony Young
|
|
|
Marty
|
DOC - Permit Finaled | 12/22/2016 | 12/22/2016 | 12/22/2016 | P | PASS |
Tony Young
|
|
|
c of o sent via e-mail to Marty
|
BLD-Final | 12/15/2016 | 12/16/2016 | 12/16/2016 | A | PART |
Tony Young
|
|
|
If needed my number is ###-#### Marty Phone #: ###-#### Inspection requested via web by Marty Pieroni///, needs fireplace final,, historical 1st,, walk through only
|
Zoning Approval | 12/16/2016 | 12/16/2016 | 12/16/2016 | | PASS |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 8/26/2016 | 8/29/2016 | 8/29/2016 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Framing/Rough-in | 8/24/2016 | 8/25/2016 | 8/24/2016 | A | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Framing/Rough-in | 8/24/2016 | 8/24/2016 | 8/24/2016 | A | PART |
Phil Shearer
|
|
|
Tony Ben said he would be finished no later then 11 wondering if you could swing by close to that time to look over, Ben''s number is ###-#### Phone #: ###-#### Inspection requested via web by Marty Pieroni. Provide engineered fix on floor joist.
|
BLD-Framing/Rough-in | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | PART |
Tony Young
|
|
|
Please call me with a time you can be there. I have engineering changes I need to bring to you for the final framing inspection thanks Phone #: ###-#### Inspection requested via web by Marty Pieroni,,, c/n.. ok to insulate
|
BLD-Framing/Rough-in | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | DEFR |
Jim Storey
|
|
|
Please call me with a time you can be there. I have engineering changes I need to bring to you for the final framing inspection thanks Phone #: ###-#### Inspection requested via web by Marty Pieroni mech failled/ defred to monday
|
BLD-Conference | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | DONE |
Jim Sly
|
|
|
Framer has questions on bracing can we have an inspector swing by to confirm a few issues please. Call myself or Ben Cicak framer at ###-####085 thanks Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Foundation | 6/9/2016 | 6/10/2016 | 6/10/2016 | A | PASS |
Dave Hannah
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 6/8/2016 | 6/9/2016 | 6/9/2016 | A | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | NR |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 5/24/2016 | 5/25/2016 | 5/26/2016 | A | PART |
Dave Hannah
|
|
|
Matt Phone #: ###-#### basement walls ok
|
BLD-Footing | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, basement footings ok
|
BLD-Footing | 5/16/2016 | 5/16/2016 | 5/16/2016 | P | CANC |
Tony Young
|
|
|
Matt Phone #: ###-####,, canc per Matt
|
Issue PAID IN FULL permit | | | 5/4/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/4/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 5/3/2016 | | |
|
|
|
|
Routing - Design Review | 5/3/2016 | | 5/3/2016 | | PASS |
Matthew A Halitsky
|
|
|
per ePlan
|
Routing - PLAN CHECK | 5/3/2016 | | 5/3/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/3/2016 | | DONE |
|
|
|
NEED RP
|
Plan assigned to (LEG) Tisha | 3/15/2016 | | 5/3/2016 | | DONE |
Tisha Gallop
|
|
|
3rd review 4/27; 2nd review 4/7; 1st review 3/25; plan check,
|
Plan resubmittals received | | | 4/29/2016 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 4/27/2016 | | 4/27/2016 | | FAIL |
Tisha Gallop
|
|
|
building review items not addressed
|
Routing - MECHANICAL | 4/20/2016 | | 4/22/2016 | | PASS |
Troy James
|
|
|
added basement
|
Routing - Design Review | 4/20/2016 | | 4/22/2016 | | PASS |
Matthew A Halitsky
|
|
|
|
Plan resubmittals received | | | 4/22/2016 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 4/20/2016 | | 4/21/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 4/7/2016 | | DONE |
|
|
|
spoke to Marty. Needs updated wall bracing plan uploaded. He also said customer now wants to add basement to plans so sent resubmittal task back over to customer to re-upload all plans affected by changes. Transfered him to Matt to discuss DR conditins
|
Routing - Design Review | 3/30/2016 | | 4/4/2016 | | FAIL |
Matthew A Halitsky
|
|
|
per ePlan
|
Routing - PLAN CHECK | 3/30/2016 | | 3/31/2016 | | FAIL |
Tisha Gallop
|
|
|
did not address previous comments
|
Plan resubmittals received | | | 3/26/2016 | | DONE |
|
|
|
|
1st review completed | | | 3/25/2016 | | FAIL |
|
|
|
pending approval by plan check and design review
|
Routing - PLAN CHECK | 3/15/2016 | | 3/25/2016 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
Routing - Design Review | 3/15/2016 | | 3/22/2016 | | FAIL |
Matthew A Halitsky
|
|
|
per ePlan
|
Route to Impact Fee Review | 3/15/2016 | 3/18/2016 | 3/16/2016 | | PASS |
Stephanie Jensen
|
|
|
|
Routing - MECHANICAL | 3/15/2016 | | 3/16/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 3/15/2016 | | 3/15/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/15/2016 | | 3/15/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/15/2016 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/15/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/2/2016 | | FAIL |
Christina Prado
|
|
|
Need Stair section, building cross section & basement floor plan
|
Application received | | | 3/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 1 2016 11:25AM
|