Case Summary (BLD) | | | 7/26/2016 | | DONE |
|
|
|
|
BLD-Final | 6/1/2016 | 6/1/2016 | 6/1/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: 2085015747 >> Inspection requested via mobile web by Thomas Lane
|
DOC - Permit Finaled | 6/1/2016 | 6/1/2016 | 6/1/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 4/21/2016 | 4/21/2016 | 4/21/2016 | P | PASS |
Mike Jordan
|
|
|
late as possible; Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 4/20/2016 | 4/20/2016 | 4/20/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/19/2016 | 4/20/2016 | 4/20/2016 | A | CANC |
Mike Jordan
|
|
|
Tom Phone #: ###-####. mOved to pm. onspection.
|
BLD-Wall Bracing | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | PASS |
Mike Jordan
|
|
|
Lane Phone #: ###-####
|
BLD-Foundation | 3/21/2016 | 3/21/2016 | 3/21/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 3/18/2016 | 3/18/2016 | 3/18/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 3/18/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/16/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 3/8/2016 | 3/8/2016 | 3/16/2016 | | DONE |
Brian McGowan
|
|
|
due 3/16 Failed. Need tall wall Engineering
|
Inspection Record Card- Bld | | | 3/16/2016 | | DONE |
|
|
|
|
Telephone call | | | 3/16/2016 | | DONE |
|
|
|
called Tom to let know permit is ready and how much is owed
|
Routing - PLAN CHECK | 3/16/2016 | | 3/16/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/16/2016 | | DONE |
|
|
|
All Met
|
1st review completed | | | 3/14/2016 | | FAIL |
Brian McGowan
|
|
|
Need tall wall Engineering
|
Case Summary (BLD) | | | 3/14/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 3/8/2016 | | 3/14/2016 | | FAIL |
Brian McGowan
|
|
|
Need tall wall Engineering
|
Routing - MECHANICAL | 3/4/2016 | | 3/8/2016 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 3/2/2016 | | 3/8/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 3/3/2016 | | 3/4/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2016 | | 3/3/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Flood Plain | 3/2/2016 | | 3/3/2016 | | PASS |
Jim Wyllie
|
|
|
LOMR
|
Routing PW Sewer Rating | 3/2/2016 | | 3/2/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 3/2/2016 | | 3/2/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/2/2016 | | DONE |
|
|
|
|
Intake Approval | | | 3/2/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/2/2016 | | DONE |
|
|
|
|
Application received | | 3/1/2016 | | | |
|
|
|
|