Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-00656
StatusFinaled
Name GRIFFIN BUILDING LTD THE
Site Address 9933 W EMERALD ST
Project NameRevenant Distribution
Customer Number 
ePlanReviewNo
Description
**(REVENANT DISTRIBUTION, LLC)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for a 2,100 sq ft existing office / light assembly / warehouse tenant. This space was previously approved as “Lucent Technologies” under BLD99-0770. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT. There will be no change to the occupancy. If racking is installed over 8 ft. a separate racking permit will be required. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/10/20163/11/20163/11/2016PPASS
DetailsMike Jordan
Logan// please call for access Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection3/10/20163/11/20163/11/2016APASS
DetailsTroy Cobbley
Life safety passed
Permanent Occupancy  3/11/2016 DONE
Routing - PLAN CHECK3/9/2016 3/10/2016 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  3/10/2016 DONE
Permit Ready to Issue  3/10/2016 DONE
Telephone call  3/10/2016 DONE
called Logan to let know permit is ready
Print Occupancy Form  3/10/2016 DONE
Issue PAID IN FULL permit  3/10/2016 DONE
Plan assigned to (TLW)3/2/2016 3/10/2016 PASS
DetailsTim L. Woodard
Routing - FIRE3/9/20163/9/20163/9/2016 PASS
DetailsKatie Marron
PDS Fire Inspector to verify sprinkler system is current on inspections. Fire alarm system is for sprinkler monitoring.
Case Summary (BLD)  3/9/2016 DONE
1st review completed  3/9/2016 PASS
Routing - PLAN CHECK3/3/2016 3/9/2016 PASS
DetailsTim L. Woodard
Routing - Addressing3/2/2016 3/3/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/3/2016 3/3/2016 PASS
DetailsJennifer Bruner
Plans ACCEPTED BY PLAN TECH  3/2/2016 DONE
Intake Approval  3/2/2016  
DetailsTim L. Woodard
Recd Pcfee & Taken To Pln CK  3/2/2016 DONE
First Notice 3/21/2016   
Application received 3/2/2016