Third Notice | | 4/16/2017 | 4/11/2017 | | DONE |
|
|
|
Sent 4-12-17
|
Second Notice | | 2/23/2017 | 3/9/2017 | | DONE |
|
|
|
|
First Notice | | 2/4/2017 | 2/13/2017 | | DONE |
|
|
|
sent in mail 2-14-17
|
Print Occupancy Form | | | 1/25/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/25/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 12/5/2016 | 12/5/2016 | 12/5/2016 | P | PASS |
Phil Shearer
|
|
|
JC Phone #: ###-####
|
BLD-Final | 12/1/2016 | 12/2/2016 | 12/2/2016 | P | PART |
Phil Shearer
|
|
|
jc Phone #: ###-#### Handrail of ramps need to be the full length of the ramp and extend 1' past the end. OK for temp
|
FIRE-Final Inspection | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, knox box is in place, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
PubWorks Occupancy Approval | 12/2/2016 | 12/2/2016 | 12/2/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 11/30/2016 | 11/30/2016 | 11/30/2016 | | |
|
|
|
|
BLD-Ceiling Grid Inspection | 11/9/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Phil Shearer
|
|
|
would like late afternoon; JC Phone #: ###-####
|
BLD-Framing/Rough-in | 10/26/2016 | 10/27/2016 | 10/27/2016 | P | PASS |
Phil Shearer
|
|
|
hard lid restrooms // JC Phone #: ###-####
|
BLD-Energy code compliance | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Phil Shearer
|
|
|
jc Phone #: ###-####
|
BLD-Framing/Rough-in | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | PASS |
Phil Shearer
|
|
|
JC Phone #: ###-####
|
BLD-Framing/Rough-in | 9/27/2016 | 9/28/2016 | 9/28/2016 | A | PASS |
Phil Shearer
|
|
|
East side of roof
|
BLD-Framing/Rough-in | 9/27/2016 | 9/27/2016 | 9/27/2016 | P | DEFR |
Phil Shearer
|
|
|
East side of roof
|
BLD-Framing/Rough-in | 9/26/2016 | 9/27/2016 | 9/27/2016 | A | PASS |
Phil Shearer
|
|
|
West side of roof
|
BLD-Framing/Rough-in | 9/26/2016 | 9/26/2016 | 9/26/2016 | P | NR |
Phil Shearer
|
|
|
|
BLD-Framing/Rough-in | 9/23/2016 | 9/26/2016 | 9/26/2016 | A | NR |
Phil Shearer
|
|
|
JC Phone #: ###-####
|
BLD-Framing/Rough-in | 9/22/2016 | 9/23/2016 | 9/23/2016 | P | NR |
Phil Shearer
|
|
|
Roof // JC Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/6/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/6/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 5/31/2016 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/31/2016 | | DONE |
Christina Prado
|
|
|
***all requirments met 6-2-16 /CEV
***Needs RP only 6-2-16 /CEV
Needs RP, GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (TLW) | 3/23/2016 | | 5/31/2016 | | PASS |
Tim L. Woodard
|
|
|
1st review complete
|
Routing PW Drainage | 5/11/2016 | | 5/26/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 5/11/2016 | | 5/26/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 5/26/2016 | | DONE |
|
|
|
O & M Appendix J taken to Brian Mu
|
Routing - PLAN CHECK | 5/11/2016 | | 5/26/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - ELECTRICAL | 5/11/2016 | | 5/12/2016 | | PASS |
Javier Guzman
|
|
|
|
Plan resubmittals received | | | 5/11/2016 | | DONE |
|
|
|
|
Routing - Design Review | 5/11/2016 | | 5/11/2016 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 4/22/2016 | 4/25/2016 | 5/2/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Drainage | 3/25/2016 | | 4/22/2016 | | FAIL |
Brian Murphy
|
|
|
NEEDS O AND M FORM J ROOF
|
1st review completed | | | 4/22/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/23/2016 | | 4/22/2016 | | FAIL |
Tim L. Woodard
|
|
|
Corrections noted as changemarks in E-Plan Review. TLW
|
Routing - PLANNING Land Div | 3/23/2016 | | 4/22/2016 | | PASS |
Tim L. Woodard
|
|
|
Approved in E-Plan Review. TLW
|
Routing Off Site - STRUCTURAL | 3/23/2016 | | 4/22/2016 | | FAIL |
Tim L. Woodard
|
|
|
Corrections noted in E-Plan Review. TLW
|
Routing - MECHANICAL | 3/23/2016 | | 4/4/2016 | | PASS |
Troy James
|
|
|
|
Routing - ELECTRICAL | 3/23/2016 | | 3/31/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 3/23/2016 | 3/23/2016 | 3/29/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Sewer Design | 3/28/2016 | | 3/28/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Private sewer collection for Riverstone. Connects at Manhole 736A in Lysted Ave.
|
Routing - PLANNING | 3/23/2016 | | 3/25/2016 | | PASS |
Susan Riggs
|
|
|
|
Routing PW Street Lights | 3/24/2016 | | 3/24/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 3/23/2016 | | 3/24/2016 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC. All Non potable water labeled as required by code.
|
Routing - Design Review | 3/23/2016 | | 3/23/2016 | | FAIL |
Andrea Tuning
|
|
|
|
Pending Assignment by TLW | 3/23/2016 | | 3/23/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Addressing | 3/23/2016 | | 3/23/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/23/2016 | | 3/23/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 3/23/2016 | | 3/23/2016 | | PASS |
Evan Jenkins
|
|
|
(Site prep inspection and approval required prior to earth disturbance)
(RIVERSTONE MIDDLE + HIGH SCHOOL - Classroom Building) Build a ±7,000 sq. ft. classroom addition to replace two aging modular buildings. This will be Phase I of the new Middle + High School building.
|
Plan Reviewer's activity | | | 3/18/2016 | | PASS |
|
|
|
Plan intake approved
|
Application received | | | 3/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 14 2016 2:52PM
|