BLD-Final | 7/14/2016 | 7/20/2016 | 7/20/2016 | A | PASS |
Phil Shearer
|
|
|
James Phone #: ###-####
|
DOC - Permit Finaled | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PASS |
Phil Shearer
|
|
|
|
Zoning Approval | 7/18/2016 | 7/18/2016 | 7/18/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 7/14/2016 | 7/14/2016 | 7/14/2016 | P | PEND |
Tony Young
|
|
|
James Phone #: ###-####,, ok pending historical approval
|
BLD-Framing/Rough-in | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PEND |
Dave Hannah
|
|
|
James Phone #: ###-#### ok to insulate after elec inspection
|
BLD-Foundation | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | DONE |
Tony Young
|
|
|
Adam Phone #: ###-####
|
BLD-Foundation | 4/18/2016 | 4/19/2016 | 4/19/2016 | A | PART |
Tony Young
|
|
|
would like call ahead; Adam Phone #: ###-####
|
BLD-Footing | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | PASS |
Tony Young
|
|
|
would like call ahead; Adam Phone #: ###-####
|
PubWorks Subgrade Approval | 4/18/2016 | 4/18/2016 | 4/18/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Plan assigned to (BJM) | 3/17/2016 | 3/17/2016 | 4/13/2016 | | DONE |
Brian McGowan
|
|
|
WUI Zone A, Class A roof, residential addition in Historic
|
Issue PAID IN FULL permit | | | 3/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/21/2016 | | |
|
|
|
|
Routing PW Grading-Hillside | 3/17/2016 | | 3/21/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Plan assigned to (BJM) | 3/21/2016 | | 3/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 3/21/2016 | | 3/21/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 3/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 3/21/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/21/2016 | | DONE |
|
|
|
Not sure if the GC turned in app or not. Left a message for John informing him that if he is not the GC we would need a revised value from the GC. If he is with Owyhee then I gave him the fee amount that is due
|
Routing Walk-In (Zoning) | 3/17/2016 | 3/17/2016 | 3/17/2016 | A | PASS |
Matthew A Halitsky
|
|
|
DRH16-00006
|
Routing Walk-In (BLD) | 3/17/2016 | 3/17/2016 | 3/17/2016 | A | FAIL |
Javier Guzman
|
|
|
Need engineering calcs for the foundation
|
1st review completed | | | 3/17/2016 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 3/17/2016 | | | |
|
|
|
|