Permit for the construction of a new 1,635 sq. ft., two story (main level 1,106 sq. ft., upper level 529 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 141 sq. ft. of covered patio’s/porches and 525 sq. ft. detached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. One side of home is 3'-0" from the property line-all projections closer than 3' must meet (1) hour fire rated construction on the underside. Prescriptive Energy Code is proposed. DRH16-00253 and 00254. **BJM**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/4/20171/5/20171/5/2017APASS
DetailsTony Young
reschedule from boise city snow day. :-) Phone #: ###-#### Inspection requested via web by zane everman
DOC - Permit Finaled1/5/20171/5/20171/5/2017PPASS
DetailsTony Young
c of o issued
BLD-Final1/2/20171/4/20171/4/2017APEND
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by zane everman city car will not get to job site
BLD-Energy code compliance10/25/201610/26/201610/26/2016APASS
DetailsTony Young
Insulation // Mike Phone #: ###-####
BLD-Framing/Rough-in10/17/201610/18/201610/18/2016PPEND
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by zane everman ok to insulate after mec rough in passes
BLD-Energy code compliance10/17/201610/18/201610/18/2016PPART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by zane everman air seal ok
BLD-Wall Bracing9/28/20169/30/20169/30/2016APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by zane everman
BLD-Foundation8/24/20168/24/20168/24/2016PPART
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, poured,, ok
BLD-Footing8/23/20168/23/20168/23/2016PPART
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, form boards are in the hole,, work in progress
Issue PAID IN FULL permit  8/17/2016 DONE
OVERRIDE  8/2/2016  
Plan assigned to (BJM)7/12/20167/12/20168/2/2016 DONE
Details
Plan assigned to (BJM)3/23/20163/23/20168/2/2016 DONE
DetailsBrian McGowan
due 4/1 - Did not submit for DR - complete new designs are expected.
Inspection Record Card- Bld  8/2/2016 DONE
Telephone call  8/2/2016 DONE
Left a messge for Mike informing him that this permit is ready, the fee amount and that we need an RP. David Wood's RP expired 1-28-16
Case Summary (BLD)  8/2/2016 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  8/2/2016 DONE
DetailsBrian McGowan
Permit Ready to Issue  8/2/2016 DONE
DetailsChristina Prado
**MET** Need RP for issuance
Routing - MECHANICAL7/27/2016 7/27/2016 PASS
DetailsTroy James
resubmitted acca report
Routing - MECHANICAL  7/22/2016 FAIL
DetailsTroy James
drawing on report does not match the resubmitted plans and orientation is wrong
Routing - PLAN CHECK  7/22/2016 PASS
DetailsBrian McGowan
Plan resubmittals received  7/13/2016 DONE
received 2 copies of sheet 1- gave to Brian
Routing - PLANNING7/13/2016 7/13/2016 PASS
DetailsSarah Schafer
Approved per submitted site plan showing attached sidewalk.
Routing - PLANNING7/12/2016 7/13/2016 FAIL
DetailsSarah Schafer
Does not comply with DRH16-00253. Specifically condition 1a requiring a 5-foot attached sidewalk. Cover sheet one shall be updated to reflect this requirement prior to sign-off.

Left a message with Mike Walker at ###-####.
Routing - Addressing7/12/2016 7/12/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS7/12/2016 7/12/2016 PASS
DetailsRachael Beierle
Plan resubmittals received  7/12/2016 DONE
received 2 complete sets of plans, 2 submittal checklists, 2 applications, 2 pplanning packets, 2 8x10 site plans, and 1 manual J- put on Brian's desk
Routing - PLAN CHECK3/22/2016 4/1/2016 FAIL
DetailsBrian McGowan
Did not submit for Design Review
1st review completed  4/1/2016 FAIL
DetailsBrian McGowan
Did not submit for Design Review
Route to Impact Fee Review3/18/20163/21/20163/23/2016 PASS
DetailsCindy M. Gould
Plan assigned to (LEG) Tisha3/18/2016 3/23/2016 DEFR
DetailsTisha Gallop
Routing - MECHANICAL3/21/2016 3/22/2016 PASS
DetailsTroy James
Routing - PUBLIC WORKS3/21/2016 3/21/2016 PASS
DetailsJennifer Bruner
Routing - Addressing3/18/2016 3/18/2016 PASS
DetailsLaura Hunter
Plans ACCEPTED BY PLAN TECH  3/18/2016 DONE
Intake Approval  3/18/2016 PASS
Recd Pcfee & Taken To Pln CK  3/18/2016 DONE
Application received 3/18/2016   
Routing - PLANNING3/21/2016   FAIL
Needs DR first