Letter of compliance/Occupancy | | | 6/14/2016 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 6/14/2016 | | |
Tony Young
|
|
|
|
BLD-Final | 5/24/2016 | 5/27/2016 | 5/27/2016 | P | PASS |
Tony Young
|
|
|
Tony, Could you please call me before coming. I have to make sure we can get in the building and then I will have a guy on site to show you where we are working. Thanks, Todd Phone #: ###-#### Inspection requested via web by Todd Kurns,, recieved e mail on special inspections,, ok
|
BLD-Final | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PART |
Tony Young
|
|
|
Tony, Could you please call me before coming. I have to make sure we can get in the building and then I will have a guy on site to show you where we are working. Thanks, Todd Phone #: ###-#### Inspection requested via web by Todd Kurns,, all ok,, just waiting for special inspection report,, Todd will e-mail to me
|
Issue PAID IN FULL permit | | | 3/28/2016 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 3/22/2016 | | 3/24/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/22/2016 | | 3/24/2016 | | PASS |
Tim L. Woodard
|
|
|
Structural Repair Permit only. TLW
|
1st review completed | | | 3/24/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/24/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/24/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/24/2016 | | DONE |
|
|
|
need GC Form
|
Inspection Record Card- Bld | | | 3/24/2016 | | DONE |
|
|
|
|
Telephone call | | | 3/24/2016 | | DONE |
|
|
|
called Todd to let know permit is ready and how much is owed-left message on his phone
|
Plans ACCEPTED BY PLAN TECH | | | 3/22/2016 | | DONE |
|
|
|
|
Intake Approval | | | 3/22/2016 | | |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/22/2016 | | DONE |
|
|
|
|
Application received | | 3/22/2016 | | | |
|
|
|
|