Scope of work is to demo exisitng detached garage and construct a new detached garage with habitable/conditioned art space above. The new garage will be 24x30 sq. ft. totaling 720 sq. ft. per level. A separate electrical and HVAC permit will be pulled by the trades. No Manual J was submitted with the plans therefore a it is assumed that a ductless HVAC system will be installed. Also, no plumbing was indicated on the plans and the plan reviewer was unable to contact the contractor or the designer during the review period to verify. If a furnace or plumbing is installed, a plan modification will be required and will need to be routed to other departments for approval. The work will be performed per the approved plans and local codes. **DAF**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/17/201610/18/201610/18/2016APASS
DetailsJim Sly
Cindy Phone #: ###-####
DOC - Permit Finaled10/18/201610/18/201610/18/2016PPASS
DetailsJim Sly
BLD-Energy code compliance8/4/20168/5/20168/5/2016APASS
DetailsJim Sly
Insulation // Fred Phone #: ###-####
BLD-Framing/Rough-in8/1/20168/1/20168/1/2016PPASS
DetailsJim Sly
Fred Phone #: ###-####
BLD-Wall Bracing6/1/20166/2/20166/2/2016APASS
DetailsJim Sly
Fred Phone #: ###-####// please call ahead
BLD-Foundation5/6/20165/9/20165/9/2016APASS
DetailsJim Sly
Nathan Phone #: ###-####
BLD-Footing5/4/20165/6/20165/6/2016APASS
DetailsJim Sly
Nate or Brent ###-#### Phone #: ###-####
BLD-Conference4/13/20164/14/20164/14/2016ADONE
DetailsJim Sly
Please call ahead for access - Fred Phone #: ###-####
Issue PAID IN FULL permit  4/7/2016 DONE
Plan assigned to (DAF)3/23/20163/23/20164/6/2016 DONE
DetailsDavid Ferguson
due 3/30 - Planning failed due to insufficient setbacks
Plan resubmittals received  4/6/2016 DONE
resubmittal recieved 5 sheets of A1-took to Dave F
Routing - PLANNING4/6/2016 4/6/2016 PASS
DetailsBruce Eggleston
PLANS/APPL TAKEN TO FRONT DESK  4/6/2016 DONE
Permit Ready to Issue  4/6/2016 DONE
Telephone call  4/6/2016 DONE
called Fred to let know the permit is ready
Routing - PLAN CHECK3/23/2016 3/30/2016 PASS
DetailsDavid Ferguson
1st review completed  3/30/2016 DONE
DetailsDavid Ferguson
Inspection Record Card- Bld  3/30/2016 DONE
DetailsDavid Ferguson
Case Summary (BLD)  3/30/2016 DONE
DetailsDavid Ferguson
Routing Walk-In (Zoning)3/22/20163/22/20163/22/2016PFAIL
DetailsBruce Eggleston
The east sideyard setback must be 20 feet. They are going to change the plan. A Zoning Certificate is required because the structure exceeds 1,000 sq. ft. it will be completed and sent to me ASAP. BPE
I received the Zoning Certificate 3/31/2016. Can't PASS BLD16-00933 until revised plan is submitted that meets the setback requirements (20 Ft.) on the street side yard. BPE
Routing Walk-In (BLD)3/22/20163/22/20163/22/2016PCANC
DetailsDavid Ferguson
Didn't want to wait so he left plans with permit techs
Intake Approval  3/22/2016  
Application received 3/22/2016