First Notice | 10/7/2016 | 10/7/2016 | 4/16/2019 | | DONE |
Dave Hannah
|
|
|
This permit finaled on the web by Dwayne Robinson
|
BLD-Final | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | PASS |
Dave Hannah
|
|
|
Duane Phone #: ###-####
|
DOC - Permit Finaled | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | PASS |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 6/10/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/10/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/13/2016 | 5/13/2016 | 6/6/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 5/19 L1 AT&T cell tower replacement antena ePlan
|
Routing - PLAN CHECK | 6/6/2016 | | 6/6/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2016 | | DONE |
|
|
|
MET Needs; GC Form Revised Cert of Value
|
Routing - PLAN CHECK | 5/13/2016 | | 5/17/2016 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 5/17/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 5/13/2016 | | 5/16/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/13/2016 | | 5/16/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 5/13/2016 | | 5/16/2016 | | PASS |
Celine Acord
|
|
|
|
Intake Approval | | | 5/13/2016 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 4/18/2016 | | FAIL |
Javier Guzman
|
|
|
1. Please provide full engineering structural calculations
2. Please provide structural engineering calculations to include the added weight to the existing building roof structure for the proposed batteries in the existing equipment shelter
|
Application received | | | 3/24/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 24 2016 1:23PM
|