BLD-Conference | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | PASS |
Mike Jordan
|
|
|
Final Side garage door is open, Owner sleeps until 12:30 PM and is home until 4PM You can go in if no one is home Thanks Paul Phone #: ###-#### Inspection requested via web by Paul Bushman
|
DOC - Permit Finaled | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 5/6/2016 | 5/6/2016 | 5/6/2016 | A | PASS |
Jim Sly
|
|
|
iNSULATION Phone #: ###-#### Inspection requested via web by Paul Bushman Insulation OK.
|
BLD-Conference | 5/4/2016 | 5/4/2016 | 5/4/2016 | A | PASS |
Jim Sly
|
|
|
Sheer ,Infiltration, framing. Phone #: ###-#### Inspection requested via web by Paul Bushman
|
BLD-Conference | 4/20/2016 | 4/20/2016 | 4/20/2016 | P | PASS |
Jim Sly
|
|
|
Footings Phone #: ###-#### Inspection requested via web by Paul Bushman Paul called gas Co. They said OK to pour footing over gas line....They will re-route around addition later. Footing OK.
|
BLD-Conference | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | FAIL |
Jim Sly
|
|
|
footings Phone #: ###-#### Inspection requested via web by Paul Bushman C/N.....Gas Co. to OK gas line running through new crawlspace
|
Routing Walk-In (Zoning) | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Brent Moore
|
|
|
|
Routing Walk-In (BLD) | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 3/28/2016 | 3/28/2016 | 3/28/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 3/28/2016 | | 3/28/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 3/28/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2016 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 3/28/2016 | | DONE |
|
|
|
|
1st review completed | | | 3/28/2016 | | DONE |
David Ferguson
|
|
|
|
Application received | | 3/28/2016 | | | |
|
|
|
|