Print Statement | | | 11/28/2016 | | DONE |
|
|
|
|
First Notice | | 10/23/2016 | 11/15/2016 | | DONE |
|
|
|
Mailed 11-16-16
|
BLD-Final | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Jim Storey
|
|
|
Please call Jim 30 min before going out. Phone #: ###-####
|
Permanent Occupancy | | | 10/13/2016 | | DONE |
|
|
|
|
BLD-Final | 10/4/2016 | 10/5/2016 | 10/6/2016 | P | PEND |
Dave Hannah
|
|
|
Jim-please call 30 minutes prior to meet Phone #: ###-#### ada restroom signage change lock on restroom door fix handrails on ext steps
|
FIRE-Final Inspection | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 10/4/2016 | 10/4/2016 | 10/4/2016 | P | CANC |
Jim Page
|
|
|
Spoke with point of contact, Jim Phone #: ###-####, informed him on what I look for with the life fire safety inspection, inspection will be rescheduled after discussed items are completed, this inspection request cancelled.
|
BLD-Framing/Rough-in | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | CANC |
Jim Storey
|
|
|
Joe Phone #: ###-####
|
BLD-Final | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | CANC |
Jim Storey
|
|
|
Joe Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/3/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/3/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/28/2016 | 3/28/2016 | 4/18/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 4/08 L2 House converted to Commercial
|
Routing - PLAN CHECK | 4/18/2016 | | 4/18/2016 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 4/18/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/18/2016 | | DONE |
|
|
|
MET ***still need GC & rev of val***Need ACHD (4-18-16), GC FORM and Revised Cert of Value
|
Print Occupancy Form | | | 4/18/2016 | | DONE |
|
|
|
|
Telephone call | | | 4/18/2016 | | DONE |
|
|
|
called Duane to let know permit is ready and that we need the GC & rev cert of rev
|
Plan resubmittals received | | | 4/14/2016 | | DONE |
|
|
|
Two copies of sheets A1, A2, A3 and S1. Taken to Javier
|
Routing - PLAN CHECK | 3/28/2016 | | 4/7/2016 | | FAIL |
Javier Guzman
|
|
|
emailed reveiw report to applicants rep
|
1st review completed | | | 4/7/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 3/28/2016 | | 3/29/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2016 | | 3/29/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 3/29/2016 | | 3/29/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 3/29/2016 | | 3/29/2016 | | PASS |
Tom Marshall
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/28/2016 | | DONE |
|
|
|
|
Intake Approval | | | 3/28/2016 | | PASS |
Javier Guzman
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/28/2016 | | DONE |
|
|
|
|
Application received | | 3/28/2016 | | | |
|
|
|
|