Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD16-01059
StatusFinaled
Name PENTALON CONSTRUCTION
Site Address 2972 E PARKCENTER BLVD
Project NameArboretum at Barber Station #2
Customer NumberBLD15-01058 & 01060
ePlanReview 
Description
(ARBORETUM AT BARBER STATION – Building #2) Permit to construct a new 123,212 square foot (5) story apartment building. First floor foundation and concrete podium permit submitted under BLD15-04486. Each floor is approximately 24,405 square feet. Approval contingent upon adhering to the approved plans on file and attached engineering. This building is fully fire sprinklered with an NFPA 13 system to comply with special provisions of section 510.2 and area increase. Scope of work includes: interior finish of the first floor, construction of wood frame 4 story building on top of the previously approved podium, installation of interior non-bearing walls and bearing walls to create 80 individual units, new plumbing, new electrical, new mechanical, new insulation, new windows, new doors, and interior finishes in compliance with Chapter 8 of the 2012 IBC. This building will be sprinklered with a fully compliant NFPA 13 system to comply with special provisions of section 510.2 and area increase. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  7/3/2018 DONE
BLD-Final6/28/20186/29/20186/29/2018APASS
DetailsJim Sly
looks like everyone has signed off but you only have a partial final
OK for perm Occ.
Zoning Approval6/28/20186/28/20186/28/2018 DONE
DetailsAndrea Tuning
Telephone call  6/26/2018 DONE
called Brian to let know temp c of o expires at the end of June-he thinks everything has been finaled-he'll check on his end and call back-all subs are finaled-this is what the building final notes said-(OK for Perm. Occ. When Electr, Mech, Plumb and Zoning signs for Perm Occ.) need sign off card
BLD-Aging Inspection4/17/20184/17/20184/23/2018 CANC
DetailsJim Sly
Temporary Occupancy4/10/20187/9/20184/10/2018 DONE
DetailsCandy A. Nichols
Jason ok'd 90 day ext from 4/1/18-kChristina said it was ok to extend even if the bond was expired
Telephone call  4/6/2018 DONE
called-talked to Brian-he's going to email Jason Blais for an estension on a temp c of o
BLD-Aging Inspection2/14/20182/14/20182/15/2018 DONE
DetailsBrandon Shaw
Work in progress
Temporary Occupancy12/27/20173/27/201812/27/2017 PASS
DetailsCandy A. Nichols
Meeting  12/27/2017 DONE
as per Jason Blais-request for extension granted good through 4/1/18
BLD-Final12/4/201712/4/201712/4/2017APART
DetailsJim Sly
Late Morning Please. Phone #: ###-#### Inspection requested via web by Michael West
OK for Temp. Occ. OK for Perm. Occ. When Electr, Mech, Plumb and Zoning signs for Perm Occ.
FIRE-Final Inspection12/4/201712/4/201712/4/2017APASS
DetailsJim Page
Building 2 fire sprinkler inspection complete, building 2 fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by main entry. Final life fire safety inspection for buidling 2 passed/complete.
Temporary Occupancy12/4/20173/4/201812/4/2017 DONE
DetailsChristina Prado
FIRE-Final Inspection11/30/201712/1/201712/1/2017AFAIL
DetailsJim Page
Fire alarm modifications not completed at time of inspection, life fire safety inspection stopped.
FIRE-Alarm Testing11/30/201712/1/201712/1/2017ACANC
DetailsJim Page
Fire alarm testing/inspection is to be requested by the installing contractor under the associated FIR permit, this request is cancelled.
Zoning Approval Temp12/1/201712/1/201712/1/2017 DONE
DetailsAndrea Tuning
FIRE-Final Inspection11/30/201711/30/201711/30/2017AFAIL
DetailsJim Page
Need 18 inches of clearance from bottom of fire sprinkler deflector to top of storage (closets and pantries are the main issue). No exterior signage for roof access or fire sprinkler riser room. Provide emergency lighting for exit discharge landings. FIR permits for both fire sprinkler and fire alarm need to be finaled before life fire safety inspection can be completed.
BLD-Final11/30/201711/30/201711/30/2017APEND
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Michael West
Pre-inspection....walk thru.
BLD-Ceiling Grid Inspection11/10/201711/13/201711/13/2017APASS
DetailsJim Sly
Level 5 and Level 4 Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in11/3/201711/3/201711/3/2017PPART
DetailsBrandon Shaw
Level 1 elevator lobby.

OK to cover
BLD-Framing/Rough-in9/21/20179/22/20179/22/2017APASS
DetailsJim Sly
Units 211-220 drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in9/18/20179/19/20179/19/2017APASS
DetailsJim Sly
Elevator lobby ceilings at levels 2 and 3. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in9/5/20179/6/20179/6/2017APASS
DetailsJim Sly
Units 311-320 Drop Ceilings Ready to cover. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in9/1/20179/1/20179/1/2017PNR
DetailsJim Sly
Units 311-320 Drop Ceilings and Soffits Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in8/24/20178/24/20178/24/2017PPASS
DetailsJim Sly
Units 411-420 soffits and drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in8/16/20178/16/20178/17/2017PPASS
DetailsJim Sly
Units 511-520 Soffits and drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in8/14/20178/14/20178/14/2017PNR
DetailsJim Sly
Units 511-520 Soffits and Drops to cover with gyp-board. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in7/18/20177/19/20177/19/2017APASS
DetailsJim Sly
Units 201-210 Phone #: ###-#### Inspection requested via web by Michael West
BLD-Conference7/18/20177/18/20177/18/2017PCANC
DetailsJim Sly
BLD-Framing/Rough-in7/14/20177/14/20177/17/2017PPART
DetailsBrandon Shaw
Level 3 drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
BLD-Energy code compliance6/29/20176/29/20176/29/2017PPASS
DetailsJim Sly
Mike West Phone #: ###-####
BLD-Energy code compliance6/29/20176/29/20176/29/2017APART
DetailsBrandon Shaw
Units 411-420 insulation
BLD-Framing/Rough-in6/21/20176/21/20176/21/2017PPART
DetailsBrandon Shaw
Units 511-520 Framing Phone #: ###-#### Inspection requested via web by Michael West
Units 511-520
CHANGE STATUS TO (ISS)  6/12/2017 DONE
DetailsChristina Prado
Change status to reflect current, cannot see reason for project being under review, no tasks show review
BLD-Framing/Rough-in6/7/20176/7/20176/7/2017PPART
DetailsJim Sly
Mike Phone #: ###-####
3rd level OK.
BLD-Framing/Rough-in6/1/20176/2/20176/2/2017APASS
DetailsJim Sly
UNits 211- thru 220 - Mike Phone #: ###-####
Routing - Design Review6/1/2017 6/1/2017 PASS
DetailsKatelyn Menuge
DRH16-00498-Window Trim Modification Okay
BLD-Framing/Rough-in5/31/20175/31/20175/31/2017PNR
DetailsJim Sly
Units 211-220 ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West
Electr. needs to complete firestopping.
BLD-Energy code compliance4/28/20175/1/20175/1/2017APASS
DetailsJim Sly
Level 3 units 301-310 Insulation ready for GWB install. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in4/25/20174/25/20174/25/2017PPART
DetailsJim Sly
Units 301-310 Ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in4/18/20174/18/20174/18/2017PPASS
DetailsJim Sly
Level 4 units 401-410 framing. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Wall cover4/13/20174/13/20174/13/2017PPASS
DetailsJim Sly
Units 501-510 Insulation Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in4/4/20174/5/20174/5/2017APART
DetailsJim Sly
Level 5 units 501-510 Framing for insulation to start Phone #: ###-#### Inspection requested via web by Michael West
BLD-Framing/Rough-in3/2/20173/2/20173/2/2017APART
DetailsJim Sly
Pre-rock corridor ceilings and 4'' down the wall at levels 2,3,4 and 5 West half of building. Phone #: ###-#### Inspection requested via web by Michael West OK
BLD-Framing/Rough-in2/28/20172/28/20172/28/2017PPART
DetailsJim Sly
Pre-rock at tubs for units 501-510 and 401-410. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Wall Bracing2/17/20172/21/20172/21/2017APART
DetailsMike Jordan
Shear walls Units401-410 Phone #: ###-#### Inspection requested via web by Michael West. Interior shear walls for corrido walls at first floor. Nailing ok. Needs to install holdowns.
BLD-Framing/Rough-in2/15/20172/16/20172/16/2017APART
DetailsJim Sly
Roof sheathing and level 5 units 501-510 shearwall nailing. Phone #: ###-#### Inspection requested via web by Michael West
OK pending MTI special inspections, tests and approvals.
BLD-Conference2/13/20172/14/20172/15/2017APEND
DetailsBob Archibald
Requesting an inspection to clarify whether the use of a generator for elevator operation in the event of a power failure is required, or if a battery backup lowering function is sufficient to meet code. Phone #: ###-#### Inspection requested via web by Michael West. Backup Power question under review.
BLD-Conference1/27/20171/31/20172/13/2017ANR
DetailsDave Hannah
Consultation to discuss inspections as we move into the framing and finishes stages. Phone #: ###-#### Inspection requested via web by Michael West
BLD-Conference12/13/201612/13/201612/13/2016PDONE
DetailsPhil Shearer
Phone #: 8013815319 >> Inspection requested via mobile web by Mike west
Place hold on job8/11/2016 8/16/2016 DONE
DetailsKristal Soland
DO NOT ISSUE WITHOUT BLD16-01058 TO BLD16-01060
Issue PAID IN FULL permit  8/16/2016 DONE
Print Occupancy Form  8/16/2016 DONE
OVERRIDE  7/19/2016  
Permit Ready to Issue  7/19/2016 DONE
DetailsChristina Prado
***ALL MET 8-11-16*** Need RP

**MET 8-10** ACHD, GC Form & Revised Certificate of Value for issuance

DO NOT ISSUE WITHOUT ALL 3 PERMITS - BLD16-01058, 01059 & 01060
Plan resubmittals received  7/18/2016 DONE
Routing - PLAN CHECK7/18/2016 7/18/2016 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  7/18/2016 DONE
Plan assigned to (TLW)4/8/2016 7/18/2016 PASS
DetailsTim L. Woodard
2nd review completed.
Routing - PLAN CHECK5/31/2016 7/5/2016 FAIL
DetailsTim L. Woodard
Routing - MECHANICAL5/31/2016 7/5/2016 PASS
DetailsTroy James
Routing - PLUMBING5/31/2016 7/5/2016 PASS
DetailsDaryl Spivey
Routing Off Site - STRUCTURAL5/31/2016 7/5/2016 PASS
DetailsTim L. Woodard
Plan resubmittals received  5/31/2016 DONE
Route to Impact Fee Review5/13/20165/16/20165/13/2016 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK4/8/2016 5/12/2016 FAIL
DetailsTim L. Woodard
Routing - PLANNING Land Div4/8/2016 5/12/2016 PASS
DetailsTim L. Woodard
Approved in E-Plan. TLW
Routing Off Site - STRUCTURAL4/8/2016 5/12/2016 FAIL
DetailsTim L. Woodard
Routing PW Drainage4/11/2016 5/12/2016 PASS
DetailsBrian Murphy
Approved in E-Plan. TLW
Routing PW Street Lights4/11/2016 5/12/2016 PASS
DetailsTom Marshall
Approved in E-Plan. TLW
Routing PW Sewer Design4/11/2016 5/12/2016 PASS
DetailsKyle S. Rosenmeyer
Approved in E-Plan. TLW
Routing PW Flood Plain4/11/2016 5/12/2016 PASS
DetailsJim Wyllie
Approved in E-Plan. TLW
Routing PW Grading-Hillside4/11/2016 5/12/2016 PASS
DetailsJim Wyllie
Approved in E-Plan. TLW
1st review completed  5/12/2016 DONE
Routing - Design Review4/8/2016 4/20/2016 PASS
DetailsJosh Wilson
Routing - MECHANICAL4/8/2016 4/18/2016 FAIL
DetailsTroy James
Routing - FIRE4/8/20164/8/20164/12/2016 PASS
DetailsKatie Marron
Comments attached to case
Routing - PLUMBING4/8/2016 4/11/2016 FAIL
DetailsDaryl Spivey
see bld16-01058 for comments
Routing - PUBLIC WORKS4/8/2016 4/11/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment4/8/2016 4/11/2016 PASS
DetailsEvan Jenkins
(Site Prep Inspection and approval required prior to earth disturbance)

BUILDING #2: Arboretum at Barber Station is a 162 unit apartment complex consisting of 3 building on a 4.07 acre site. Buildings 1 & 2 are podium structures with 4 stories of apartments in Type 5A wood construction over 1 story of Type 1A post-tension concrete structure. Building 3 is a two story Type 5B wood construction with 1 level of apartment units over tenant amenities.

A separate structural podium permit application has been filed for Buildings 1 and 2.
Routing PW Solid Waste4/11/2016 4/11/2016 PASS
DetailsMegan Durrell
Routing - Addressing4/8/2016 4/8/2016 PASS
DetailsLaura Hunter
Intake Approval  4/8/2016 PASS
Application received  3/31/2016 DONE
Application submitted via PDS Online on Mar 31 2016 4:48PM
First Notice 7/13/2018