Second Notice | | 10/27/2016 | 11/14/2016 | | DONE |
|
|
|
Mailed 11-15-16
|
First Notice | 9/22/2016 | 9/22/2016 | 10/17/2016 | | DONE |
Jim Sly
|
|
|
Mailed 10-18-16
|
BLD-Final | 9/21/2016 | 9/22/2016 | 9/22/2016 | A | PASS |
Jim Sly
|
|
|
Please call Phill when on site. ###-#### Phone #: ###-#### Inspection requested via web by Philip Allen
|
DOC - Permit Finaled | 9/22/2016 | 9/22/2016 | 9/22/2016 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Philip Allen Inspection cancelled from web by: Philip Allen
|
BLD-Final | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | PART |
Jim Sly
|
|
|
Meat/ Seafood Department Final. Please Call Phil when on site ###-#### Phone #: ###-#### Inspection requested via web by Philip Allen Partial.......OK to occupy Seafood Dept.
|
FIRE-Final Inspection | 9/7/2016 | 9/8/2016 | 9/8/2016 | A | PART |
Troy Cobbley
|
|
|
Life Safety for Seafood Department passed.
|
BLD-Framing/Rough-in | 8/26/2016 | 8/29/2016 | 8/29/2016 | A | PART |
Jim Sly
|
|
|
Seafood Drop Soffit Framing. Please call Phil when on site. ###-#### Phone #: ###-#### Inspection requested via web by Philip Allen Seafood Soffit OK.
|
BLD-Final | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | PART |
Jim Sly
|
|
|
BLDG Final- Deli Call Phil when here ###-#### Phone #: ###-#### Inspection requested via web by Philip Allen Deli OK to occupy.
|
FIRE-Conference | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | DONE |
Troy Cobbley
|
|
|
Went over life safety requirements with Phil
|
FIRE-Final Inspection | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | PART |
Troy Cobbley
|
|
|
Fire life safety for the new Deli area passed.
|
BLD-Framing/Rough-in | 7/25/2016 | 7/25/2016 | 7/25/2016 | A | PART |
Jim Sly
|
|
|
Framing inspection for pharmacy wall framing. Phil Allen is day superintendent Phone #: ###-#### Inspection requested via web by Ron Hack Pharmacy....OK
|
BLD-Framing/Rough-in | 6/14/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Jim Sly
|
|
|
Please call Phil Allen when on site ###-#### Phone #: ###-#### Inspection requested via web by Philip Allen
|
BLD-Framing/Rough-in | 5/22/2016 | 5/23/2016 | 5/23/2016 | A | PASS |
Mike Jordan
|
|
|
Please call when on site. Framing for new CCK ; Teller rooms adjacent to Electronics in front of store. Phone #: ###-#### Inspection requested via web by Philip Allen. iNterior steel stud framed walls and hardlid for new CCK and teller rooms.
|
Issue PAID IN FULL permit | | | 5/17/2016 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2016 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/5/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 4/7/2016 | 4/7/2016 | 5/5/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - Fred Meyer
|
Routing - PLAN CHECK | 5/5/2016 | | 5/5/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/5/2016 | | DONE |
|
|
|
***ALL MET 5-16-16*** Needs; RP, GC Form, Revised Cert of Value
|
Routing - PLAN CHECK | 5/4/2016 | | 5/4/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
change mark not completely addressed. called and left message with applicant
|
Routing - PLAN CHECK | 5/3/2016 | | 5/3/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
not all change marks addressed
|
1st review completed | | | 5/2/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 4/7/2016 | | 5/2/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Environmental | 4/8/2016 | | 4/19/2016 | | PASS |
Rick Christenson
|
|
|
On-site inspection after work is completed.
|
Routing - MECHANICAL | 4/7/2016 | | 4/12/2016 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 4/7/2016 | 4/7/2016 | 4/11/2016 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing PW Sewer Rating | 4/8/2016 | | 4/8/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLUMBING | 4/7/2016 | | 4/8/2016 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required at the RO system and hose reel.
|
Routing - PUBLIC WORKS | 4/7/2016 | | 4/8/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 4/7/2016 | | 4/8/2016 | | PASS |
Evan Jenkins
|
|
|
FRED MEYER) Minor interior tenant improvement consisting of relocation of equipment an providing new equipment. Relocating interior walls. Color fixture plans have been included for clarity.
|
Intake Approval | | | 4/7/2016 | | FAIL |
David Ferguson
|
|
|
1) All plan sheets must be uploaded into ePlan horizontally. There are two sheets that are vertical. Please upload these horizontally.
2) It appears that the scope of work include over 40 ft. of concrete trenching. This will require an ESC Waiver Letter explaining how you propose to dispose of these materials.
3) The #518 checklist must be filled out completely. Please refer to the energy portion of the checklist where you've indicated that you've provided information but did not indicate on which page that information can be found.
|
Intake Approval | | | 4/7/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Dave Ferguson and plan review fees paid.
|
Pending Assignment by JCB | 4/7/2016 | | 4/7/2016 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 4/7/2016 | | 4/7/2016 | | PASS |
Laura Hunter
|
|
|
|
Application received | | | 4/4/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 4 2016 12:56PM
|