Meeting | | | 5/11/2018 | | |
|
|
|
sent statement 5-14
|
Print Statement | | | 5/11/2018 | | DONE |
|
|
|
|
Print Statement | | | 3/20/2018 | | DONE |
|
|
|
|
Third Notice | | 2/17/2018 | 3/14/2018 | | DONE |
|
|
|
Mailed 3-15-18
|
Second Notice | | 1/21/2018 | 2/12/2018 | | DONE |
|
|
|
Mailed 2-13-18
|
First Notice | | 12/17/2017 | 1/11/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
Permanent Occupancy | | | 12/7/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/5/2017 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 11/6/2017 | | DONE |
|
|
|
No outstanding permit issues all trades have been finaled. Ok for perm. occ.
|
Plan Reviewer's activity | | | 11/3/2017 | | DONE |
Jason Blais
|
|
|
Received another Commissioning Report Summary updated on the project. A few remaining items being worked on but can be relsolved between the commissioning agent and the owner (City PW/Fire).
|
BLD-Final | 4/27/2017 | 4/28/2017 | 4/28/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
FIRE-Final Inspection | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Zoning Approval | 4/28/2017 | 4/28/2017 | 4/28/2017 | | DONE |
Sarah Schafer
|
|
|
|
BLD-Final | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt 2nd floor tank handle
|
FIRE-Final Inspection | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | CANC |
Troy Cobbley
|
|
|
still waiting for the fire alarm permit to be addressed
|
BLD-Final | 4/25/2017 | 4/26/2017 | 4/26/2017 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt Need all Fire Inspections prior to calling for Structural final. Called Kevin......unable to leave V/M message.
|
FIRE-Final Inspection | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire sprinkler and fire alarm permits are passed.
|
PubWorks Occupancy Approval | 4/25/2017 | 4/25/2017 | 4/25/2017 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 | P | FAIL |
Troy Cobbley
|
|
|
I went over life safety requirements with the project superintendant since alarms and sprinkler permits were not ready. There is a short list of corrections marked in red on the Fire Review Notes.
|
BLD-Ceiling Grid Inspection | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Ceiling Grid Inspection | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Framing/Rough-in | 1/31/2017 | 1/31/2017 | 1/31/2017 | P | PASS |
Jim Storey
|
|
|
Level 2 framing inspection Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Wall cover | 1/23/2017 | 1/23/2017 | 1/23/2017 | P | PASS |
Jim Storey
|
|
|
Ready whenever you can get here. AM ok if needed. Thanks Phone #: ###-#### Inspection requested via web by Kevin Honeycutt 1 st floor ok
|
BLD-Framing/Rough-in | 1/17/2017 | 1/17/2017 | 1/17/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt. 1st. floor interior steel stud framed walls and hardlids ok. Pending M.E.P inspections in the p.m.
|
BLD-Framing/Rough-in | 1/12/2017 | 1/13/2017 | 1/13/2017 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Framing/Rough-in | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt exterior ok
|
BLD-Framing/Rough-in | 11/21/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt sw first floor exterior ok to cover exterior
|
BLD-Conference | 10/3/2016 | 10/7/2016 | 10/7/2016 | A | PART |
Mike Jordan
|
|
|
12:30 grout. Strata onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt.. Pending special inspection.
|
BLD-Conference | 10/3/2016 | 10/6/2016 | 10/6/2016 | A | PART |
Jim Sly
|
|
|
12:30 grout. Strata onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt OK pending STRATA special inspection, tests and approvals.
|
BLD-Conference | 10/3/2016 | 10/5/2016 | 10/5/2016 | A | PEND |
Phil Shearer
|
|
|
12:30 grout. Strata onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Conference | 10/3/2016 | 10/4/2016 | 10/4/2016 | A | PEND |
Mike Jordan
|
|
|
12:30 grout. Strata onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt. Pending special inspection.
|
BLD-Conference | 9/30/2016 | 10/3/2016 | 10/3/2016 | A | PEND |
Mike Jordan
|
|
|
12:30 wall grout. Strata to be onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Conference | 9/28/2016 | 9/30/2016 | 9/30/2016 | A | PEND |
Dave Hannah
|
|
|
12:30 grout. Strata to be onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt ok after spec inspection signoff
|
BLD-Conference | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Jim Sly
|
|
|
12:30 grout. Strata to be onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt OK pending STRATA special inspection, tests and approvals.
|
BLD-Conference | 9/27/2016 | 9/28/2016 | 9/28/2016 | A | PASS |
Jim Storey
|
|
|
12:30 wall grout. Strata will be onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt placed w/si
|
BLD-Conference | 9/26/2016 | 9/26/2016 | 9/26/2016 | P | PASS |
Jim Storey
|
|
|
Wall grout at 11AM. Strata and EOR to be onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Conference | 9/21/2016 | 9/21/2016 | 9/21/2016 | A | PASS |
Jim Storey
|
|
|
Wall grout at 11 AM. Strata will be onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt si pending
|
BLD-Conference | 9/19/2016 | 9/20/2016 | 9/20/2016 | A | PASS |
Jim Storey
|
|
|
11 AM Grout. Strata will be onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt pwsi
|
BLD-Conference | 9/15/2016 | 9/16/2016 | 9/16/2016 | A | DONE |
Jim Storey
|
|
|
11AM grout. Strata will be onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Conference | 9/12/2016 | 9/14/2016 | 9/14/2016 | A | PART |
Jim Storey
|
|
|
Grout at 11 AM. Strata will be onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt placed wth si
|
BLD-Conference | 9/8/2016 | 9/13/2016 | 9/12/2016 | A | CANC |
Jim Storey
|
|
|
11 AM grout scheduled Phone #: ###-#### >> Inspection requested via web by Kevin Honeycutt Inspection cancelled from web by: Kevin Honeycutt
|
BLD-Conference | 9/8/2016 | 9/9/2016 | 9/9/2016 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt cmu east wall 1st lift/ wip/ si pending
|
BLD-Foundation | 7/26/2016 | 7/27/2016 | 7/27/2016 | P | PART |
Jim Storey
|
|
|
Site contact Ted Walker - ###-#### Inspection of footings prepared for concrete placement at Boise Fire Station #8. Concrete placement currently scheduled for Thursday (7/28/16) at 09:00 am. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
Place hold on job | 6/23/2016 | | 6/30/2016 | | DONE |
Kristal Soland
|
|
|
Make sure Deom is FNL BLD16-01045
|
Issue PAID IN FULL permit | | | 6/30/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/30/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/22/2016 | | |
|
|
|
|
Routing - PLAN CHECK | 6/16/2016 | | 6/22/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/16/2016 | | 6/22/2016 | | PASS |
Tim L. Woodard
|
|
|
Uploaded approval sheet by Outsource in Documents folder of E-Plan. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/22/2016 | | DONE |
|
|
|
All requirements met 6/30/16 C_P
NEED ACHD ***MET** GC & rev cert of val and RP
|
Plan assigned to (TLW) | 4/18/2016 | | 6/22/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Drainage | 6/16/2016 | | 6/17/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 6/16/2016 | | 6/17/2016 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Plan resubmittals received | | | 6/16/2016 | | DONE |
|
|
|
|
1st review completed | | | 5/26/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/18/2016 | | 5/26/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/18/2016 | | 5/26/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing PW Street Lights | 4/18/2016 | | 5/26/2016 | | PASS |
Tom Marshall
|
|
|
Approved in E-Plan Review. TLW
|
Routing PW Environmental | 4/18/2016 | | 5/5/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 4/18/2016 | | 5/3/2016 | | PASS |
Troy James
|
|
|
Green Building Review Required. TLW
|
Routing - Design Review | 4/18/2016 | | 4/21/2016 | | PASS |
Josh Wilson
|
|
|
Green Building Review ok per SMS.
|
Routing PW Drainage | 4/18/2016 | | 4/21/2016 | | FAIL |
Brian Murphy
|
|
|
needs city o and m agreement per D. Strickling
|
Routing - FIRE | 4/18/2016 | 4/18/2016 | 4/19/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Solid Waste | 4/18/2016 | | 4/19/2016 | | PASS |
Megan Durrell
|
|
|
As designed this FS will be limited to a max of 4, 95 gallon wheeled carts for trash/recycling with no future option of a dumpster. It is preferred to design for the future/unknown.
|
Routing - Erosion and Sediment | 4/18/2016 | | 4/19/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep inspection and approval required prior to earth disturbance)
**Project Management - Ron Hill** **GREEN TAG Expidited Review - GREEN BUILDING CODE**(CITY OF BOISE - Fire Station #8) Permit to construct a new 11,936 square foot 2 story fire station and related site work.
|
Routing - PLUMBING | 4/18/2016 | | 4/19/2016 | | FAIL |
Daryl Spivey
|
|
|
Green Building Review Required. TLW
change the FS-1 to a FS-2 and increase the waste line to a 4" to accept the discharge of the 1 1/2" RP on the non-potable water lne in room 107.
|
Routing - PLANNING Land Div | 4/18/2016 | | 4/19/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 4/18/2016 | | 4/18/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/18/2016 | | 4/18/2016 | | PASS |
Rachael Beierle
|
|
|
Green Building Review Required. TLW
|
Intake Approval | | | 4/18/2016 | | PASS |
|
|
|
|
Pending Assignment by TLW | 4/18/2016 | | 4/18/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Design | 4/18/2016 | | 4/18/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Application received | | | 4/5/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 5 2016 8:14AM
|