BLD-Final | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Tony Young
|
|
|
Chuck Phone #: ###-####
|
PubWorks Occupancy Approval | 10/20/2016 | 10/20/2016 | 10/20/2016 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 9/29/2016 | 9/30/2016 | 9/30/2016 | P | PART |
Tony Young
|
|
|
Chuck Phone #: ###-####,, temp. occ. ok
|
FIRE-Final Inspection | 9/30/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PART |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags, correct signage is in place. Patial final for life fire safety inspection complete, life safety can be signed off as complete after fire department inspection has been completed and passed.
|
Zoning Approval | 9/29/2016 | 9/29/2016 | 9/29/2016 | | PASS |
Josh Wilson
|
|
|
|
PubWorks Occupancy Approval | 9/29/2016 | 9/29/2016 | 9/29/2016 | | DONE |
Jason C. Taylor
|
|
|
PW Temporary occupancy approved. Special inspections of flume lid will need to be performed to PW satidfaction prior to fianl sign-off. Jason Taylor ###-####
|
BLD-Conference | 9/28/2016 | 9/28/2016 | 9/28/2016 | P | PEND |
Tony Young
|
|
|
per 325 ,, need special inspection reports to public works,, talked w/ Chuck,, he was taking care of this today
|
BLD-Foundation | 9/15/2016 | 9/16/2016 | 9/16/2016 | A | PART |
Tony Young
|
|
|
Chuck Phone #: ###-####,, special inspector on site
|
BLD-Footing | 7/29/2016 | 8/1/2016 | 8/1/2016 | A | CANC |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Footing | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | PASS |
Dave Hannah
|
|
|
Pouring at 10 // Chuck Phone #: ###-#### four canopy foundations
|
BLD-Concrete | 7/25/2016 | 7/25/2016 | 7/25/2016 | P | PART |
Tony Young
|
|
|
Brad Phone #: ###-####,, ramp and steps foundation ok
|
BLD-Footing | 7/18/2016 | 7/19/2016 | 7/19/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: 9892465 >> Inspection requested via mobile web by Brad
|
Issue PAID IN FULL permit | | | 7/11/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/11/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/27/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 4/18/2016 | 4/18/2016 | 6/27/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/27/2016 | | DONE |
|
|
|
***Still needs ACHD
NEED GC form, cerificate of value, ACHD, and RP
|
Routing PW Flood Plain | 5/25/2016 | | 6/27/2016 | | PASS |
Jim Wyllie
|
|
|
Signed off per E-plan
|
Routing - PLAN CHECK | 6/23/2016 | | 6/23/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 5/25/2016 | | 6/20/2016 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 6/17/2016 | | 6/17/2016 | | PASS |
Beverly Mountain
|
|
|
|
Routing Off Site - STRUCTURAL | 5/24/2016 | | 6/7/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 5/24/2016 | | 6/7/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 5/25/2016 | | 5/31/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 5/24/2016 | | 5/25/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Grading-Hillside | 4/18/2016 | | 5/25/2016 | | FAIL |
Jason C. Taylor
|
|
|
SENT TO JASON PER JEW
|
Routing PW Flood Plain | 4/18/2016 | | 5/25/2016 | | FAIL |
Jim Wyllie
|
|
|
|
Route to Impact Fee Review | 5/2/2016 | 5/5/2016 | 5/2/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 4/18/2016 | | 5/2/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 4/18/2016 | | 5/2/2016 | | FAIL |
Jason C. Taylor
|
|
|
See hillside changemarks. JCT
|
Routing PW Street Lights | 4/18/2016 | | 5/2/2016 | | CANC |
Tom Marshall
|
|
|
No review required per E-plan
|
Routing - PLAN CHECK | 4/18/2016 | | 5/2/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 5/2/2016 | | FAIL |
|
|
|
|
Routing PW Environmental | 4/18/2016 | | 5/2/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Sewer Design | 4/18/2016 | | 4/27/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Show the abandonment and plug of the existing sewer service to the property. Add note: "Contact Boise Public Works 48 hours prior to capping existing sewer service at property line to obtain plug permit and schedule inspection."
|
Routing PW Solid Waste | 4/18/2016 | | 4/20/2016 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLANNING Land Div | 4/18/2016 | | 4/20/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Design Review | 4/18/2016 | | 4/20/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 4/18/2016 | | 4/19/2016 | | PASS |
Daryl Spivey
|
|
|
plumbing approved with canopy drains discharging to surface
|
Routing - Erosion and Sediment | 4/18/2016 | | 4/19/2016 | | PASS |
Evan Jenkins
|
|
|
Demolition of existing Chevron gas station and replacement with new fuel canopy. This canopy will be serviced from our existing c-store to the north. Existing underground fuel tanks will remain.
|
Routing - FIRE | 4/18/2016 | 4/18/2016 | 4/18/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Addressing | 4/18/2016 | | 4/18/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/18/2016 | | 4/18/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 4/18/2016 | | PASS |
|
|
|
|
Pending Assignment by TLW | 4/18/2016 | | 4/18/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 4/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 6 2016 10:30AM
|