BLD-Final | 8/2/2016 | 8/2/2016 | 8/2/2016 | P | DONE |
Tony Young
|
|
|
Barrie Phone #: ###-####
|
DOC - Permit Finaled | 8/2/2016 | 8/2/2016 | 8/2/2016 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/19/2016 | 7/19/2016 | 7/19/2016 | P | FAIL |
Phil Shearer
|
|
|
Barrie Phone #: ###-#### Need landing and driveway
|
BLD-Framing/Rough-in | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Phil Shearer
|
|
|
Bob Phone #: ###-####
|
BLD-Wall Bracing | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####
|
BLD-Footing | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/28/2016 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 4/27/2016 | 4/27/2016 | 4/27/2016 | P | PASS |
Colleen T Carroll
|
|
|
|
Plan assigned to (DAF) | 4/11/2016 | 4/11/2016 | 4/27/2016 | | DONE |
David Ferguson
|
|
|
Demo permit needs to be finaled prior to issuing building permit. Also, need letter from the Canal company.
|
Case Summary (BLD) | | | 4/27/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/27/2016 | | DONE |
|
|
|
Needs; GC Form & RP
|
Case Summary (BLD) | | | 4/27/2016 | | DONE |
|
|
|
|
Telephone call | | | 4/27/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
Routing Walk-In (BLD) | 4/11/2016 | 4/11/2016 | 4/11/2016 | P | FAIL |
David Ferguson
|
|
|
Demo permit needs to be finaled prior to issuing building permit. Also, letter from the Canal company.
|
1st review completed | | | 4/11/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 4/11/2016 | | 4/11/2016 | | FAIL |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 4/11/2016 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 4/11/2016 | | DONE |
David Ferguson
|
|
|
|
Application received | | 4/11/2016 | | | |
|
|
|
|