Second Notice | | 7/21/2016 | 7/26/2016 | | DONE |
|
|
|
This permit finaled on the web by Carissa Primmer
|
First Notice | | 6/12/2016 | 7/11/2016 | | DONE |
|
|
|
Mailed 7-12
|
Permanent Occupancy | | | 6/2/2016 | | DONE |
|
|
|
|
BLD-Final | 6/1/2016 | 6/1/2016 | 6/1/2016 | P | PASS |
Mike Jordan
|
|
|
Please call Sid. Phone #: ###-#### Inspection requested via web by Carissa Primmer. Ok for perm occ.
|
FIRE-Final Inspection | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 5/4/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Phil Shearer
|
|
|
Sid Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/4/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/4/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/18/2016 | 4/18/2016 | 4/29/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 4/29 L2 Catholic Charities of Idaho ePlan
|
Routing - PLAN CHECK | 4/29/2016 | | 4/29/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/29/2016 | | DONE |
Christina Prado
|
|
|
All requirements met 4/29/16 /// C_P
Need GC Form and Revised Cert of Value
|
Routing - PLAN CHECK | 4/18/2016 | | 4/27/2016 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 4/27/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 4/18/2016 | | 4/18/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/18/2016 | | 4/18/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 4/18/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 4/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 15 2016 2:17PM
|