Permit Information
Permit NumberBLD16-01382
StatusFinaled
Name PETRA INC
Site Address 4195 N EAGLE RD
Project NameStoragePlus Inc. Bldg B
Customer NumberBLD16-01291 EPLAN, 1382 - 01389
ePlanReview 
Description
(STORAGE PLUS - Bldg B - Self Storage) (9 PERMITS TOTAL FILED UNDER BLD16-01291 IN EPLANREVIEW) Permit for the construction of a new 2,250 sq. ft. storage building B with a total of 15 storage units. This building is not fire sprinklered. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  4/26/2017 DONE
Left a message for Ian to give me a call about final values. Gave a ele value, but can't find permit and have mec permit but gave no value
First Notice 3/27/20174/11/2017 DONE
Sent 4-12-17
Permanent Occupancy  3/17/2017 DONE
BLD-Final3/15/20173/16/20173/16/2017PPASS
DetailsJim Sly
Ian Phone #: ###-#### no ele at this building OK for Perm Occ.
Zoning Approval3/16/20173/16/20173/16/2017 DONE
DetailsSarah Schafer
Temporary Occupancy1/20/20174/20/20171/20/2017 DONE
DetailsBrittany Hill
Permanent Occupancy pending final Zoning & Landscape approval. BND16-00114 is in place for landscape improvements
BLD-Final1/19/20171/19/20171/19/2017PPASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by J.C. Murray
OK for Perm Occ.
FIRE-Final Inspection1/13/20171/13/20171/13/2017PPASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final12/16/201612/16/201612/16/2016PNR
DetailsJim Sly
jake Phone #: ###-####
Need Fire Final.
BLD-Framing/Rough-in10/26/201610/27/201610/27/2016APASS
DetailsJim Sly
Jake Phone #: ###-####
(F) Reprint permit  9/23/2016 DONE
Print Occupancy Form  9/23/2016 DONE
BLD-Footing9/1/20169/2/20169/2/2016PPART
DetailsJim Sly
bldg b; Milton Phone #: ###-####
OK pending MTI special inspection, tests and approvals.
Issue PAID IN FULL permit  6/29/2016 DONE
Print Occupancy Form  6/29/2016 DONE
Permit Ready to Issue  6/28/2016 DONE
all requirments met
Plan assigned to (CDM)4/25/20164/25/20166/24/2016 PASS
DetailsCarl D Madsen
First review completed
Routing - PLANNING4/25/2016 6/24/2016 PASS
DetailsTed Vanegas
signed off per eplan
PLANS/APPL TAKEN TO FRONT DESK  6/24/2016 DONE
Routing - PUBLIC WORKS6/24/2016 6/24/2016 PASS
DetailsRachael Beierle
Routing PW Sewer Design6/20/2016 6/20/2016 PASS
DetailsKyle S. Rosenmeyer
Routing PW Drainage4/26/2016 6/20/2016 PASS
DetailsBrian Murphy
Routing PW Street Lights4/26/2016 6/20/2016 PASS
DetailsTom Marshall
Routing PW Solid Waste4/26/2016 6/20/2016 PASS
DetailsMegan Durrell
Routing - PLANNING Land Div4/25/2016 6/17/2016 PASS
DetailsTodd Tucker
Routing - PLAN CHECK6/17/2016 6/17/2016 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL6/17/2016 6/17/2016 PASS
DetailsCarl D Madsen
Route to Impact Fee Review6/1/20166/4/20166/3/2016 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK4/25/2016 6/1/2016 FAIL
DetailsCarl D Madsen
1st review completed  6/1/2016 FAIL
Routing Off Site - STRUCTURAL4/25/2016 6/1/2016 FAIL
DetailsCarl D Madsen
Routing - Erosion and Sediment4/25/2016 5/4/2016 CANC
DetailsEvan Jenkins
No ESC Permit Required. Please Refer to ESC16-00522 for coverage for entire project.
Routing - Design Review4/25/2016 4/29/2016 PASS
DetailsJosh Wilson
Routing - FIRE4/25/20164/25/20164/27/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing PW Sewer Design4/26/2016 4/27/2016 FAIL
DetailsKyle S. Rosenmeyer
Sewer in North Chapala Way: Replace cleanout at property line with manhole. Label manhole 627G11.
Key Note 26: Contact Boise Public Works 48 hours prior to capping sewer service at property line to obtain plug permit and schedule inspection.
Routing - PUBLIC WORKS4/25/2016 4/26/2016 PASS
DetailsJennifer Bruner
Routing - PLUMBING4/25/2016 4/25/2016 PASS
DetailsBill VanDegrift
Intake Approval  4/25/2016 PASS
Pending Assignment by TLW4/25/2016 4/25/2016 DONE
DetailsTim L. Woodard
Routing - Addressing4/25/2016 4/25/2016 PASS
DetailsLaura Hunter
Application received 4/22/2016