Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-01387
StatusFinaled
Name PETRA INC
Site Address 4195 N EAGLE RD
Project NameStoragePlus Inc. Bldg G
Customer NumberBLD16-01291 EPLAN, 1382 - 01389
ePlanReview 
Description
(STORAGE PLUS - Bldg G - Self Storage) (9 PERMITS TOTAL FILED UNDER BLD16-01291 IN EPLANREVIEW) Permit for the construction of a new 8,000 sq. ft. self storage building with a total of 56 units per the approved plans and the attached engineering. This building is not fire sprinklered. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 6/17/20176/22/2017 DONE
This permit finaled on the web by Ian Franklin
Third Notice 5/15/20176/12/2017 DONE
Mailed 6-13-17
Second Notice 4/21/20175/10/2017 DONE
sent in mail 5-11-17
First Notice 3/27/20174/11/2017 DONE
Mailed 4-12-17
Permanent Occupancy  3/17/2017 DONE
BLD-Final3/15/20173/16/20173/16/2017PPASS
DetailsJim Sly
Ian Phone #: ###-####
OK for Perm Occ.
BLD-Aging Inspection3/14/20173/14/20173/16/2017 CANC
DetailsJim Sly
Zoning Approval3/16/20173/16/20173/16/2017 DONE
DetailsSarah Schafer
Temporary Occupancy1/13/20174/13/20171/13/2017 DONE
DetailsChristina Prado
BLD-Final1/12/20171/12/20171/12/2017PPART
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by J.C. Murray
**Needs Zoning approval first 1/13/17 C_P**
BLD-Final1/5/20171/6/20171/6/2017ANR
DetailsJim Sly
jake Phone #: ###-####
Need Mech Final.
FIRE-Final Inspection1/3/20171/4/20171/4/2017APASS
DetailsTroy Cobbley
life safety passed
BLD-Final12/16/201612/16/201612/16/2016PNR
DetailsJim Sly
jake Phone #: ###-####
Need Fire Final.
FIRE-Final Inspection12/8/201612/8/201612/8/2016PFAIL
DetailsTroy Cobbley
need to repair the exit discharge lights and clear the fire dept access
Zoning Approval Temp12/1/201612/1/201612/1/2016 PASS
DetailsJosh Wilson
Landscape bond is in place.
BLD-Framing/Rough-in10/26/201610/27/201610/27/2016APASS
DetailsJim Sly
Jake Phone #: ###-####
(F) Reprint permit  9/23/2016 DONE
Print Occupancy Form  9/23/2016 DONE
BLD-Foundation8/24/20168/25/20168/26/2016PPART
DetailsJim Sly
Milton Phone #: ###-####
Select footing/slab OK Pending MTI special inspections, tests and approvals.
Issue PAID IN FULL permit  6/29/2016 DONE
Print Occupancy Form  6/29/2016 DONE
Permit Ready to Issue  6/28/2016 DONE
all requirments met
Plan assigned to (CDM)4/25/20164/25/20166/24/2016 PASS
DetailsCarl D Madsen
First review completed
Routing - PLANNING4/25/2016 6/24/2016 PASS
DetailsTed Vanegas
Signed off per eplan
Routing - PUBLIC WORKS6/24/2016 6/24/2016 PASS
DetailsRachael Beierle
PLANS/APPL TAKEN TO FRONT DESK  6/24/2016 DONE
Routing PW Sewer Design6/20/2016 6/20/2016 PASS
DetailsKyle S. Rosenmeyer
Routing PW Drainage4/26/2016 6/20/2016 PASS
DetailsBrian Murphy
Routing PW Street Lights4/26/2016 6/20/2016 PASS
DetailsTom Marshall
Routing PW Solid Waste4/26/2016 6/20/2016 PASS
DetailsMegan Durrell
Routing - PLANNING Land Div4/25/2016 6/17/2016 PASS
DetailsTodd Tucker
Routing - PLAN CHECK6/17/2016 6/17/2016 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL6/17/2016 6/17/2016 PASS
DetailsCarl D Madsen
Route to Impact Fee Review6/1/20166/4/20166/3/2016 PASS
DetailsCindy M. Gould
1st review completed  6/1/2016 FAIL
Routing - PLAN CHECK4/25/2016 6/1/2016 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL4/25/2016 6/1/2016 FAIL
DetailsCarl D Madsen
Routing - Erosion and Sediment4/25/2016 5/4/2016 CANC
DetailsEvan Jenkins
No ESC Permit Required. Please Refer to ESC16-00522 for coverage for entire project.
Routing - MECHANICAL5/3/2016 5/3/2016 PASS
DetailsTroy James
Routing - Design Review4/25/2016 4/29/2016 PASS
DetailsJosh Wilson
Routing - FIRE4/25/20164/25/20164/27/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing PW Sewer Design4/26/2016 4/27/2016 FAIL
DetailsKyle S. Rosenmeyer
Sewer in North Chapala Way: Replace cleanout at property line with manhole. Label manhole 627G11.
Key Note 26: Contact Boise Public Works 48 hours prior to capping sewer service at property line to obtain plug permit and schedule inspection.
Routing - PUBLIC WORKS4/25/2016 4/26/2016 PASS
DetailsJennifer Bruner
Routing - PLUMBING4/25/2016 4/25/2016 PASS
DetailsBill VanDegrift
Intake Approval  4/25/2016 PASS
Pending Assignment by TLW4/25/2016 4/25/2016 DONE
DetailsTim L. Woodard
Routing - Addressing4/25/2016 4/25/2016 PASS
DetailsLaura Hunter
Application received 4/22/2016