First Notice | | 12/29/2016 | 2/3/2017 | | DONE |
|
|
|
|
Print Statement | | | 2/3/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/19/2016 | | DONE |
|
|
|
|
Telephone call | | | 12/19/2016 | | DONE |
|
|
|
called Greg to let know the C of O is ready
|
BLD-Final | 12/15/2016 | 12/16/2016 | 12/16/2016 | A | PASS |
Jim Storey
|
|
|
Greg Phone #: ###-#### final ok no card on site
|
Print Occupancy Form | | | 12/16/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/29/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Jim Page
|
|
|
Lasr remaining item for life fire safety inspection was the racking permit, racling permit is finaled for life safety. Final life fire safety inspection passed/complete.
|
BLD-Final | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Jim Storey
|
|
|
Phone #: 2086318644 >> Inspection requested via mobile web by Greg Bolton final ok pending ele temp
|
FIRE-Final Inspection | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspections are complete, final fire alarm inspection is complete, fire extinguishers are in place with current inspection tags. Partial final for life fire safety complete, storage racking located in the southeast section of tenant space has a racking permit (BLD16-03245) in under review status, life fire safety cannot be finaled until racking permit inspection is performed and passed.
|
Extend Permit 90/180 days | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | CANC |
Jim Page
|
|
|
|
FIRE-Final Inspection | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled. Need emergency lights and exit discharge lights repaired and tested. Fire extinguishers, door hardware and address appear ok. Need a permit applied for on the high piled/storage racks. Greg Phone #: ###-####
|
Plan Reviewer's activity | | | 8/31/2016 | | DONE |
Jason Blais
|
|
|
Talked to architect. They are working on a separate racking permit submittal. Would like a Temp CO if can get all other items corrected and trade permits squared away. Will not use the racking until permitted and inspected.
|
Zoning Approval | 8/30/2016 | 8/30/2016 | 8/30/2016 | | DONE |
Cody Riddle
|
|
|
No inspection required.
|
BLD-Ceiling Grid Inspection | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | PASS |
Jim Storey
|
|
|
Greg Phone #: ###-####
|
BLD-Footing | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | PART |
Jim Storey
|
|
|
Greg Phone #: ###-#### pending si
|
BLD-Footing | 6/9/2016 | 6/10/2016 | 6/10/2016 | P | CANC |
Jim Storey
|
|
|
Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Jim Storey
|
|
|
Greg Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/19/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/19/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 5/18/2016 | | |
|
|
|
|
Routing - FIRE | 5/17/2016 | 5/17/2016 | 5/18/2016 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Plan assigned to (AJS) | 4/28/2016 | 4/28/2016 | 5/18/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - Albertsons Set Store
|
Plan Reviewer's activity | | | 5/18/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
I called Chris, the engineers revised calculations need to be stamped and signed.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/18/2016 | | DONE |
|
|
|
***ALL MET*** NEED GC form, RP, and certificate of value
|
Routing - PLAN CHECK | 5/17/2016 | | 5/18/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 5/17/2016 | | 5/18/2016 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 5/17/2016 | | 5/17/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and approval required prior to earth disturbance)
(ALBERTSONS - SET STORE) Add office area, store staging area, restroom core, and loading dock to existing building shell. Minor demolition of exterior wall and site to accommodate new construction.
|
Routing - PLAN CHECK | 4/28/2016 | | 5/13/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 5/13/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLANNING | 5/5/2016 | | 5/5/2016 | | PASS |
Cody Riddle
|
|
|
Similar to retail/office use. Allowed in commercial zone.
|
Routing - FIRE | 4/28/2016 | 4/28/2016 | 5/3/2016 | | FAIL |
Scott Arellano
|
|
|
Report attached to case and emailed to architect.
|
Routing - MECHANICAL | 4/28/2016 | | 5/3/2016 | | FAIL |
Troy James
|
|
|
|
Routing PW Drainage | 4/29/2016 | | 5/2/2016 | | PASS |
Brian Murphy
|
|
|
NOT LARGE ENOUGH
|
Routing - PLUMBING | 4/28/2016 | | 5/2/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Sewer Rating | 4/29/2016 | | 4/29/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 4/28/2016 | | 4/29/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 4/28/2016 | | 4/28/2016 | | PASS |
Laura Hunter
|
|
|
|
Pending Assignment by JCB | 4/28/2016 | | 4/28/2016 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 4/26/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Intake Approval | | | 4/25/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see mark ups on 520 check list.
|
Application received | | | 4/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 22 2016 3:58PM
|
Routing - Erosion and Sediment | 4/28/2016 | | | | FAIL |
Andy J. Long
|
|
|
ESC plan narrative references wrong address and site speicific information. Need to submit ESC plan specific to the site for the project.
|