Information based on query as of Sunday, June 23, 2024.
Permit Information
Permit NumberBLD16-01417
StatusFinaled
Name TAHOE HOMES LLC
Site Address 3681 E PARKCENTER BLVD
Project Name 
Customer NumberBLD16-01416, 01418, 01419
ePlanReviewNo
Description
WUI Valley, Zone "B", Class "A" roof required. Prescriptive Energy Code is Proposed. Permit for the construction of a new 2164 sq. ft., three story (first story 418 sq. ft., second story 838 sq. ft., third story 908) townhouse with 3 bedrooms, 3 bathrooms, approximately 235 sq. ft. of covered patio’s/porches and 490 sq. ft. attached garage per the approved plans, plan review report and any notations. SP-01 zoning and setbacks per planning. **BJM**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/5/20171/5/20171/5/2017PPASS
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by joey benart
DOC - Permit Finaled1/5/20171/5/20171/5/2017PPASS
DetailsPhil Shearer
BLD-Energy code compliance10/31/201611/1/201611/1/2016APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by joey benart
BLD-Framing/Rough-in10/30/201610/31/201610/31/2016APASS
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by joey benart
BLD-Wall Bracing10/4/201610/4/201610/4/2016APASS
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by joey benart
BLD-Wall Bracing10/3/201610/3/201610/3/2016PFAIL
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by joey benart
BLD-Conference8/30/20168/30/20168/30/2016ADONE
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by joey benart
Place hold on job5/26/2016 5/27/2016 DONE
DetailsBrittany Hill
DO NOT ISSUE WITHOUT BLD16-01416, 01418 AND 01419
Issue PAID IN FULL permit  5/27/2016 DONE
OVERRIDE  5/26/2016  
Plan assigned to (BJM)4/28/20164/28/20165/26/2016 DONE
DetailsBrian McGowan
due 5/16 L2 Townhouse
Inspection Record Card- Bld  5/26/2016 DONE
Routing - PLAN CHECK5/26/2016 5/26/2016 PASS
DetailsBrian McGowan
Case Summary (BLD)  5/26/2016 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  5/26/2016 DONE
DetailsBrian McGowan
Permit Ready to Issue  5/26/2016 DONE
All Met
Telephone call  5/26/2016 DONE
called Leonard to let know permits are ready and how much is owed-left message on phone
Plan resubmittals received  5/17/2016 DONE
Received two sets of revised plans sheets marked 3.0, 6.0, 9.0 & 9.1; Plans stamped and taken to BJM for review
1st review completed  5/13/2016 FAIL
DetailsBrian McGowan
Fire wall at cantilevered porches need to be modified
Routing - PLAN CHECK5/4/2016 5/13/2016 FAIL
DetailsBrian McGowan
Fire wall at cantilevered porches need to be modified
Routing - MECHANICAL4/28/2016 5/4/2016 PASS
DetailsTroy James
Routing - PLANNING4/25/2016 4/28/2016 PASS
DetailsJosh Wilson
Plan assigned to (LEG) Tisha4/25/2016 4/28/2016 DEFR
DetailsTisha Gallop
Routing - Addressing4/25/2016 4/25/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS  4/25/2016 PASS
Plans ACCEPTED BY PLAN TECH  4/25/2016 DONE
Intake Approval  4/25/2016 PASS
Recd Pcfee & Taken To Pln CK  4/25/2016 DONE
Application received 4/25/2016