Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD16-01422
StatusFinaled
Name ALLEN RICHARD & SHARON TRUST
Site Address 6555 W OVERLAND RD Unit: 106
Project NameVape Train
Customer Number 
ePlanReviewNo
Description
(VAPE TRAIN) This building does not have a fire sprinkler system. Application for inspection to determine the requirements for the issuance of a Certificate of Occupancy for an existing 653 square foot tenant space to be used for the retail sales of E-cigarettes and E-cigarette products. This tenant space was previously used for bail bonds and tattoos. For the sales area, egress is directly to the outside at grade. No new work is authorized under this permit except for minor work that may be needed to correct noncompliant conditions that may exist. Painting, carpeting, counter tops, and similar finish work are not required to have a permit. The change of occupancy classification from a B Occupancy to an M Occupancy is allowed under this permit since the occupant load and the tenant space is so small. A separate racking permit is required for racks over 8 feet tall. Compliance is required with the items listed in the plan review report under Referenced Code Sections because noncompliance with these items is believed to constitute a distinct hazard to life and safety. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  5/24/2016 DONE
DetailsChristina Prado
BLD-Final5/20/20165/23/20165/23/2016PPASS
DetailsMike Jordan
Alex Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection5/23/20165/23/20165/23/2016PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection5/20/20165/23/20165/23/2016AFAIL
DetailsTroy Cobbley
Need to mount the new fire extinguisher and provide annual inspection.
Issue PAID IN FULL permit  4/28/2016 DONE
(F) Reprint permit  4/28/2016 DONE
Plan assigned to (CJW)4/26/2016 4/27/2016 PASS
DetailsCarl Westfall
(April 27 - 3 days)
Routing - PLAN CHECK4/26/2016 4/27/2016 PASS
DetailsCarl Westfall
1st review completed  4/27/2016 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/27/2016 DONE
Permit Ready to Issue  4/27/2016 DONE
Print Occupancy Form  4/27/2016 DONE
Telephone call  4/27/2016 DONE
Spoke with teresita informing him that this permit is ready to be picked up and which ever tech he sees will go over the inspections that are required
Routing - Addressing4/26/2016 4/26/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS4/26/2016 4/26/2016 PASS
DetailsJennifer Bruner
Plans ACCEPTED BY PLAN TECH  4/26/2016 DONE
Intake Approval  4/26/2016  
DetailsCarl Westfall
Recd Pcfee & Taken To Pln CK  4/26/2016 DONE
Application received 4/25/2016