BLD-Final | 12/30/2016 | 1/3/2017 | 1/3/2017 | A | PASS |
Jim Storey
|
|
|
Call 30 mins before to meet // George Phone #: ###-####
|
DOC - Permit Finaled | 1/3/2017 | 1/3/2017 | 1/3/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 12/30/2016 | 12/30/2016 | 12/30/2016 | | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | PASS |
Jim Storey
|
|
|
Charley Phone #: ###-####
|
BLD-Framing/Rough-in | 8/15/2016 | 8/16/2016 | 8/16/2016 | A | PASS |
Jim Storey
|
|
|
Charley Phone #: ###-####
|
Plan Modification Accepted | | | 8/12/2016 | | PASS |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/12/2016 | | 8/12/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 7/15/2016 | 7/18/2016 | 7/18/2016 | A | PART |
Jim Storey
|
|
|
George Phone #: ###-####1st floor ok pending garage
|
BLD-Foundation | 7/1/2016 | 7/5/2016 | 7/5/2016 | P | PASS |
Dave Hannah
|
|
|
Sebastian Phone #: ###-####
|
BLD-Footing | 6/29/2016 | 6/30/2016 | 6/30/2016 | A | PASS |
Jim Storey
|
|
|
Sebastian Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/29/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/3/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 5/3/2016 | 5/3/2016 | 6/3/2016 | | DONE |
Brian McGowan
|
|
|
due 5/11 -Failed 5-10-16 - spread footings, wall bracing and truss layout clarification needed. Failed Mechanical too.
|
Routing - PLAN CHECK | 6/3/2016 | | 6/3/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 6/3/2016 | | 6/3/2016 | | PASS |
Troy James
|
|
|
|
Case Summary (BLD) | | | 6/3/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/3/2016 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Bld | | | 6/3/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/3/2016 | | DONE |
|
|
|
called George- let him know that permit is ready and fees due
|
Plan resubmittals received | | | 6/2/2016 | | DONE |
|
|
|
received 2 full sets of plans, wall-bracing, and engineering- gave to Brian
|
Routing - PLANNING | 5/10/2016 | | 5/10/2016 | | PASS |
Josh Wilson
|
|
|
Second floor pop-outs on south side for window only- no window seat or floor space allowed.
|
1st review completed | | | 5/10/2016 | | FAIL |
Brian McGowan
|
|
|
No footings specified for concentrated load bearing points, no wall bracing calcs., need truss layout,
|
Routing - PLAN CHECK | 5/5/2016 | | 5/10/2016 | | FAIL |
Brian McGowan
|
|
|
No footings specified for concentrated load bearing points, no wall bracing calcs., need truss layout,
|
Routing - MECHANICAL | 5/2/2016 | | 5/5/2016 | | FAIL |
Troy James
|
|
|
the square footage on report does not match the submitted plans.
|
Plan resubmittals received | | | 5/5/2016 | | DONE |
|
|
|
resubmittlas recieved 1 copy of prescriptive form energy and took it to Troy J as per Brian
|
Plan assigned to (LEG) Tisha | 4/27/2016 | | 5/3/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 4/27/2016 | | 5/2/2016 | | PASS |
Josh Wilson
|
|
|
Ok per DRH08-00345, CVA08-00016
|
Routing - Addressing | 4/27/2016 | | 4/27/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 4/27/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/27/2016 | | DONE |
|
|
|
|
Intake Approval | | | 4/27/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/27/2016 | | DONE |
|
|
|
|
Application received | | 4/26/2016 | | | |
|
|
|
|