Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-01451
StatusFinaled
Name NORMA MARTINEZ
Site Address 350 N MILWAUKEE Unit: 2021
Project NameEl Cazo
Customer Number 
ePlanReviewNo
Description
(EL CAZO MEXICAN FOOD – BOISE TOWN SQUARE MALL - SUITE 2021 – 2ND STORY - NEXT TO THE FOOD COURT) This building has a fire sprinkler system because it is a Mall. Application for inspection to determine the requirements for the issuance of a Certificate of Occupancy for an existing 620 square foot food preparation and food service tenant space located next to the food court at the Boise Town Square Mall. This tenant space was previously occupied by “Gaucho’s”. No new work is authorized under this permit except for minor work that may be needed to correct noncompliant conditions that may exist. Painting, carpeting, counter tops, and similar finish work are not required to have a building permit. Compliance is required with the items listed in the plan review report under Referenced Code Sections because noncompliance with these items is believed to constitute a distinct hazard to life and safety. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  6/22/2016 DONE
BLD-Final5/27/20165/31/20165/31/2016APASS
DetailsMike Jordan
Norma Phone #: ###-####
FIRE-Final Inspection5/26/20165/27/20165/27/2016APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection5/18/20165/19/20165/19/2016AFAIL
DetailsTroy Cobbley
Provide bi-annual inspection for the hood suppression system and replace the painted sprinkler pendants at the Service Counter.
Issue PAID IN FULL permit  5/16/2016 DONE
Permit Ready to Issue  5/4/2016 DONE
Print Occupancy Form  5/4/2016 DONE
Telephone call  5/4/2016 DONE
Spoke with Norma informing her that this permit is ready to be picked up and which ever tech she sees will go over the inspections needed for occupancy
Plan assigned to (CJW)4/27/20164/27/20165/3/2016 PASS
DetailsCarl Westfall
(April 29 - 3 days)
Routing - PLAN CHECK4/27/2016 5/3/2016 PASS
DetailsCarl Westfall
Routing - FIRE5/3/2016 5/3/2016 PASS
DetailsKatie Marron
Comments attached to application.
1st review completed  5/3/2016 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/3/2016 DONE
Plans ACCEPTED BY PLAN TECH  4/27/2016 DONE
Intake Approval  4/27/2016 PASS
Recd Pcfee & Taken To Pln CK  4/27/2016 DONE
Routing - Addressing4/27/2016 4/27/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS4/27/2016 4/27/2016 PASS
DetailsJennifer Bruner
No Envirnmental Review required per Terry Alber. jkb
Application received 4/26/2016