Print Statement | | | 7/21/2017 | | DONE |
|
|
|
|
First Notice | | 6/23/2017 | 7/12/2017 | | DONE |
|
|
|
sent in mail 7-13-17
|
Print Occupancy Form | | | 6/13/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 6/13/2017 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 5/23/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/14/2016 | | DONE |
|
|
|
|
BLD-Final | 11/18/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Dave Hannah
|
|
|
George Phone #: ###-####
|
BLD-Final | 11/14/2016 | 11/15/2016 | 11/16/2016 | A | PEND |
Dave Hannah
|
|
|
John Phone #: ###-#### city needs a letter from structal engineer
|
FIRE-Final Inspection | 11/14/2016 | 11/15/2016 | 11/15/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags, property has a knox box. Final life fire safety inspection complete.
|
BLD-Final | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | NR |
Phil Shearer
|
|
|
Call prior to going Phone #: 8013302634 >> Inspection requested via mobile web by Josh Oviatt. Need fire life/ safty inspection
|
Print Occupancy Form | | | 10/25/2016 | | DONE |
|
|
|
|
BLD-Conference | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | DONE |
Dave Hannah
|
|
|
Call prior to going Phone #: 8013302634 >> Inspection requested via mobile web by Josh Oviatt
|
Issue PAID IN FULL permit | | | 7/21/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/21/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/7/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 5/2/2016 | 5/2/2016 | 7/7/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) IMPERIAL PLAZA - (May 20 - 15 days) Level 3 TI - ePlanReview
|
Routing - PLAN CHECK | 7/6/2016 | | 7/7/2016 | | PASS |
Carl Westfall
|
|
|
Note - finish the 4th plan review report and upload after structural approves
|
Routing Off Site - STRUCTURAL | 7/7/2016 | | 7/7/2016 | | PASS |
Carl Westfall
|
|
|
Jared Bauder (CH2MHill)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/7/2016 | | DONE |
|
|
|
***MET 7-7-16 CAN***need RP, GC & rev cert of val
|
Routing - PLAN CHECK | 6/29/2016 | | 7/6/2016 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 6/30/2016 | | 7/6/2016 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder
|
Plan resubmittals requested | | | 7/6/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/6/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/29/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/2/2016 | | 6/9/2016 | | FAIL |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 6/9/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/9/2016 | | 6/9/2016 | | PASS |
Andy J. Long
|
|
|
ESC site plan and narrative submitted and approved. RP with Wadsworth Construction has valid WPCM Certificate from AGC /ITD
|
Routing Off Site - STRUCTURAL | 6/6/2016 | | 6/8/2016 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder
|
Routing - Erosion and Sediment | 6/6/2016 | | 6/7/2016 | | FAIL |
Andy J. Long
|
|
|
No ESC plan or ESC plan waiver submitted. Significant demolition and concrete work and Level 3 TI requires ESC permit application with plan or plan waiver document.
|
Plan resubmittals received | | | 6/2/2016 | | DONE |
Carl Westfall
|
|
|
|
Route to Impact Fee Review | 5/18/2016 | 5/21/2016 | 5/23/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 5/2/2016 | | 5/18/2016 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
1st review completed | | | 5/18/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/18/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/2/2016 | | 5/16/2016 | | FAIL |
Carl Westfall
|
|
|
See IBC plan review report
|
Routing - Erosion and Sediment | 5/2/2016 | | 5/4/2016 | | FAIL |
Evan Jenkins
|
|
|
ESC Waiver Letter Request Required for Approval.
Evan Jenkins 794.3958
|
Routing - FIRE | 5/2/2016 | 5/2/2016 | 5/3/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Addressing | 5/2/2016 | | 5/3/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2016 | | 5/3/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 5/2/2016 | | 5/2/2016 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - parking deck repairs
Parking deck repairs approved for DR through the building permit.
|
Intake Approval | | | 5/2/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Javier Guzman and plan review fees paid.
|
Pending Assignment by JCB | 5/2/2016 | | 5/2/2016 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 4/27/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2016 5:27PM
|
Zoning Approval | 5/23/2017 | 5/23/2017 | | | |
Sarah Schafer
|
|
|
planting inspection for final planning sign off
|