BLD-Final | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Jim Storey
|
|
|
Call Dan for access Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 10/12/2016 | 10/12/2016 | 10/12/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Wall cover | 8/16/2016 | 8/18/2016 | 8/18/2016 | P | PASS |
Jim Storey
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 8/16/2016 | 8/18/2016 | 8/18/2016 | P | PASS |
Jim Storey
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 8/15/2016 | 8/16/2016 | 8/16/2016 | A | PASS |
Jim Storey
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel fur out 2nd floor and ceilling fireblk not done. ok to insulate
|
BLD-Framing/Rough-in | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | NR |
Jim Storey
|
|
|
After 3 pm Dan Phone #: ###-#### Inspection requested via web by Daniel Appel framing and ceilling fire blk at duct chase 2nd floor/ no air seal.
|
Plan Modification Accepted | | | 8/8/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/8/2016 | | 8/8/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | PASS |
Jim Storey
|
|
|
Staple nailing alternate specs onsite and complete Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall Bracing | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | NR |
Jim Storey
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Foundation | 6/20/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Jim Storey
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 6/17/2016 | 6/20/2016 | 6/20/2016 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 6/16/2016 | 6/17/2016 | 6/17/2016 | A | NR |
Phil Shearer
|
|
|
Dane Phone #: ###-####
|
Inspection Record Card- Bld | | | 6/15/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/15/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 5/10/2016 | | |
|
|
|
|
Routing - Design Review | 5/10/2016 | | 5/10/2016 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 5/10/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/10/2016 | | 5/10/2016 | | PASS |
Tisha Gallop
|
|
|
|
1st review completed | | | 5/10/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/10/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan assigned to (LEG) Tisha | 4/29/2016 | | 5/10/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 5/10; 1-hr soffit & planning setback
|
Routing - PLAN CHECK | 4/29/2016 | | 5/10/2016 | | FAIL |
Tisha Gallop
|
|
|
need 1-hr soffit detail
|
Routing - MECHANICAL | 4/29/2016 | | 5/4/2016 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/29/2016 | 5/2/2016 | 5/2/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/29/2016 | | DONE |
|
|
|
|
Intake Approval | | | 4/29/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/29/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 4/29/2016 | | 4/29/2016 | | FAIL |
Andrea Tuning
|
|
|
Rear setback must be a minmum of 8-feet.
|
Routing - Addressing | 4/29/2016 | | 4/29/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/29/2016 | | 4/29/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 4/28/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 28 2016 4:03PM
|