Override - Parcel Holds | | | 7/5/2016 | | |
|
|
|
|
Permanent Occupancy | | | 7/5/2016 | | DONE |
|
|
|
|
BLD-Final | 6/29/2016 | 6/30/2016 | 6/30/2016 | P | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 6/23/2016 | 6/29/2016 | 6/29/2016 | P | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 6/21/2016 | 6/23/2016 | 6/23/2016 | P | PASS |
Katie Marron
|
|
|
Verified previous correction items. Life safety Pass.
|
FIRE-Final Inspection | 6/17/2016 | 6/20/2016 | 6/20/2016 | A | FAIL |
Katie Marron
|
|
|
Full walk thru completed. The following correction items noted: - Address numbers on front (Targee) side - Remove or replace e-light at 2nd floor office area - FE at 2nd flr office area (2A rated ok) and shop loft area - Repair exit sign from office area - Remove thumb turn deadbolts on designated exit doors
|
Override - Parcel Holds | | | 6/6/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/6/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/29/2016 | 4/29/2016 | 6/2/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 5/05 L2 DENNIS DILLON RV, Occ Eval paper
|
Routing - PLAN CHECK | 6/2/2016 | | 6/2/2016 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 6/2/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2016 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 6/2/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 6/2/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/2/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/2/2016 | | DONE |
|
|
|
Left a message for Jason informing him this permit is ready to be picked up and which ever tech he sees will go over the two inspections required for the occupancy
|
Routing - FIRE | 5/2/2016 | 5/2/2016 | 5/3/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to application.
|
1st review completed | | | 5/3/2016 | | FAIL |
Javier Guzman
|
|
|
|
Plan Reviewer's activity | | | 5/3/2016 | | DONE |
Javier Guzman
|
|
|
called applicant requesting an existing floor plan with the addition that was not shown
|
Routing - PLAN CHECK | 5/2/2016 | | 5/3/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2016 | | 5/2/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 4/29/2016 | | 4/29/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/29/2016 | | DONE |
|
|
|
|
Intake Approval | | | 4/29/2016 | | PASS |
Javier Guzman
|
|
|
|
Override - Parcel Holds | | | 4/29/2016 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/29/2016 | | DONE |
|
|
|
|
First Notice | | 7/15/2016 | | | |
|
|
|
|
Application received | | 4/29/2016 | | | |
|
|
|
|