Print Statement | | | 11/30/2016 | | DONE |
|
|
|
|
Second Notice | | 10/20/2016 | 11/15/2016 | | DONE |
|
|
|
Mailed 11-16-16
|
First Notice | | 10/10/2016 | 10/10/2016 | | DONE |
|
|
|
mailed 10-11-16
|
BLD-Final | 9/29/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Dave Hannah
|
|
|
Richard Phone #: ###-####
|
FIRE-Final Inspection | 9/29/2016 | 9/30/2016 | 9/30/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 9/30/2016 | | DONE |
|
|
|
|
BLD-Final | 9/28/2016 | 9/29/2016 | 9/29/2016 | P | NR |
Mike Jordan
|
|
|
Richard Phone #: ###-####. Life/safety final failed.
|
FIRE-Final Inspection | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or notes on site. Fire extinguishers need annual inspection tag, Door hardware, exit signs, emergnecy lights and exit discharge lights worked. Fire alarm permit is finaled.
|
Zoning Approval | 8/17/2016 | 8/17/2016 | 8/17/2016 | | DONE |
Celine Acord
|
|
|
inspection approved. loading zone lane designated with paint and signs, tree plantings for mitigation CYA
|
BLD-Foundation | 7/19/2016 | 7/20/2016 | 7/20/2016 | A | PASS |
Jim Storey
|
|
|
Kyle Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/20/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/20/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/17/2016 | | |
|
|
|
|
Print Occupancy Form | | | 6/17/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/17/2016 | | DONE |
|
|
|
Left a message for Pat that this permit is ready and what we need for issuance. RP, GC Form and Revised Value. Informed him that he would need to get with ACHD to figure out the fees required by them and if an inspection is required. Told him that he could either pay with them and bring in the receipt or bring in a letter stating the fee amount and pay for everything with us.
|
Permit Ready to Issue | | | 6/17/2016 | | DONE |
|
|
|
***ACHD is in doc****NEED RP, ACHD & GC & rev cert of val
|
Route to Impact Fee Review | 6/14/2016 | 6/17/2016 | 6/16/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (TLW) | 5/13/2016 | | 6/16/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 6/16/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/16/2016 | | 6/16/2016 | | PASS |
Tim L. Woodard
|
|
|
Emailed addendum is attached to front sheet to add additional stairs off the landing of the modular. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/16/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/7/2016 | | 6/14/2016 | | FAIL |
Tim L. Woodard
|
|
|
Egress path reconverges prior to arriving at the public way. **TLW**
|
1st review completed | | | 6/14/2016 | | DONE |
|
|
|
|
Routing - FIRE | 6/6/2016 | | 6/7/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to plans.
|
Routing - PLUMBING | | | 6/6/2016 | | PASS |
Daryl Spivey
|
|
|
1) install a cleanout on the sewer outside of the building.
2) DCVA and thermol expansion required by Suez Water on the service.
|
Routing - PLANNING | 6/6/2016 | | 6/6/2016 | | PASS |
Celine Acord
|
|
|
|
Routing - ELECTRICAL | | | 6/3/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | | | 6/2/2016 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 6/2/2016 | | 6/2/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted and approved. Valid PD, RP to be determined when contractor is determined.
|
Routing PW Drainage | 5/16/2016 | | 6/2/2016 | | PASS |
Brian Murphy
|
|
|
NO INSPECTION REQUIRED
|
Routing PW Sewer Rating | 5/16/2016 | | 5/16/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING Land Div | 5/13/2016 | | 5/16/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 5/16/2016 | | 5/16/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/13/2016 | | DONE |
|
|
|
|
Intake Approval | | | 5/13/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/13/2016 | | DONE |
|
|
|
|
Application received | | | 5/2/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 2 2016 9:57AM
|