Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-01515
StatusFinaled
Name CONGER MANAGEMENT GROUP
Site Address 2851 S FEDERAL WAY
Project NameCitadel 5 Storage - Bldg "I"
Customer NumberBLD16-01652 THRU BLD16-01665 & 1691
ePlanReviewYes
Description
(CITADEL 5 STORAGE)(BUILDING "I")(16 PERMITS TOTAL FILED UNDER BLD16-01515 IN EPLANREVIEW)Special Inspection Required. Building "I" is a 14,072 sq ft metal stroage building separated by a 3 hour fire barrier to create fire area less than 12,000 sq ft.. Building structures to be erected on an approximate 5 acre site to be completely occupied by a totally enclosed self storage facility that is bound on the north by South Federal Way and to the west and south by West Victory Road. Scope of work shall include all associated site work. This facility is NOT fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 3/9/20173/10/2017 DONE
sent in mail 3-13-17
Permanent Occupancy  2/27/2017 DONE
BLD-Final2/23/20172/24/20172/24/2017PPASS
DetailsJim Storey
After 2 // Steve Phone #: ###-####
FIRE-Final Inspection2/23/20172/24/20172/24/2017APASS
DetailsJim Page
Previously noted items have been repaired, no fire sprinklers, no fire aarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete
BLD-Final2/21/20172/22/20172/22/2017ANR
DetailsDave Hannah
Call when going to be there // Steve Phone #: ###-#### needs fire first
FIRE-Final Inspection2/21/20172/21/20172/21/2017PFAIL
DetailsJim Page
No fire extinguishers mounted in corridors of interior storage units, fire extinguishers need to be mounted per note number 1 of the fire code review comments, a total of 7 need to be installed.
PubWorks Occupancy Approval1/19/20171/19/20171/19/2017 DONE
DetailsTiffany Lowery
Zoning Approval1/13/20171/13/20171/13/2017 DONE
DetailsAndrea Tuning
BLD-Other1/10/20171/11/20171/11/2017PPASS
DetailsJim Storey
Steve// fire wall insp Phone #: ###-#### gyp base layer ok
BLD-Aging Inspection12/2/201612/2/201612/2/2016 PASS
DetailsJim Storey
BLD-Foundation7/21/20167/21/20167/21/2016PPASS
DetailsJim Storey
Wall // Manuel Phone #: ###-####
BLD-Footing7/20/20167/20/20167/20/2016PPASS
DetailsJim Storey
Manuel Phone #: ###-####
Place hold on job7/11/2016 7/12/2016 DONE
DetailsCarlos Velazquez
DO NOT ISSUE WITHOUT BLD16-01515, BLD16-01652 TO BLD16-01655 AND BLD16-01691
Issue PAID IN FULL permit  7/12/2016 DONE
Print Occupancy Form  7/12/2016 DONE
OVERRIDE  7/11/2016  
Plan assigned to (AJS)5/18/20165/18/20167/11/2016 PASS
DetailsAdele J Schaffeld-Griffin
1st Review completed Building I
Routing - PLAN CHECK7/6/2016 7/11/2016 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  7/11/2016 DONE
Permit Ready to Issue  7/11/2016 DONE
***all requirments met 7-12-16 /CEV

Needs GC form & Revised Cert of Value
Routing - PLAN CHECK6/20/2016 6/28/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL6/20/2016 6/27/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing - FIRE6/20/20166/20/20166/20/2016 PASS
DetailsKatie Marron
Signed off on all individual permits. Revised report attached to each case.
Routing - Erosion and Sediment6/20/2016 6/20/2016 PASS
DetailsEvan Jenkins
Route to Impact Fee Review6/8/20166/11/20166/10/2016 PASS
DetailsCindy M. Gould
1st review completed  6/8/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK5/18/2016 6/8/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Solid Waste5/18/2016 6/7/2016 PASS
DetailsPeter J. McCullough
Routing Off Site - STRUCTURAL5/18/2016 5/26/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Grading-Hillside5/18/2016 5/24/2016 CANC
DetailsJason C. Taylor
No review required, not hillside project. JCT
Routing - FIRE5/18/20165/18/20165/23/2016 FAIL
DetailsScott Arellano
Attached comments to plans. Emailed applicant plan review report.
Routing PW Sewer Design5/18/2016 5/20/2016 PASS
DetailsKyle S. Rosenmeyer
Routing PW Street Lights5/18/2016 5/19/2016 PASS
DetailsTom Marshall
No street light required.
Routing - PLANNING Land Div5/18/2016 5/19/2016 PASS
DetailsTodd Tucker
Routing - Addressing5/18/2016 5/19/2016 PASS
DetailsLaura Hunter
Routing - MECHANICAL5/18/2016 5/19/2016 PASS
DetailsTroy James
Redlined gas pipe sizing
Routing - PLUMBING5/18/2016 5/18/2016 PASS
DetailsDaryl Spivey
Provide 3 in. minimum to W/C and No branch lines to be taken off before DCVA.
Routing - Design Review5/18/2016 5/18/2016 PASS
DetailsAndrea Tuning
Pending Assignment by TLW5/18/2016 5/18/2016 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS5/18/2016 5/18/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment5/18/2016 5/18/2016 FAIL
DetailsEvan Jenkins
Full ESC Narrative Required: SWPPP is Required to meet Federal EPA Requirements due to the project being over 1 Acre in Disturbance Size (5 Acres), which the City will accept for this project.
Evan Jenkins 794.3958
Routing PW Drainage5/18/2016 5/18/2016 PASS
DetailsBrian Murphy
Intake Approval  5/13/2016 PASS
Intake Approval  5/4/2016 FAIL
5-4-16 Carl Madsen ###-####
Form 30 is required to be signed by the owner
Several sheets have been uploaded in the wrong orientation please re-upload the sheets in the correct orientation.
Please provide on the cover sheet a building code analysis for each building in the complex to include individual building areas, occupancy classification, occupant loads and type of construction for each building.
Application received  5/2/2016 DONE
Application submitted via PDS Online on May 2 2016 11:42AM