First Notice | | 11/18/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Permanent Occupancy | | | 11/8/2017 | | DONE |
|
|
|
|
BLD-Final | 10/11/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Ok for perm occ.
|
PubWorks Occupancy Approval | 10/12/2017 | 10/12/2017 | 10/12/2017 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 8/23/2017 | 8/24/2017 | 8/24/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Zoning Approval | 8/21/2017 | 8/21/2017 | 8/21/2017 | | DONE |
Leon Letson
|
|
|
|
FIRE-Final Inspection | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | FAIL |
Troy Cobbley
|
|
|
Provide single action hardware for the interior doors, provide tagged/mounted fire entinguishers as discussed and marked on the plans. Provide fire dept. signage as discussed.
Doug Phone #: ###-####
|
BLD-Final | 8/16/2017 | 8/18/2017 | 8/18/2017 | A | NR |
Mike Jordan
|
|
|
Doug or ###-####-please call whgen on way Phone #: ###-####. Needs fire/life/safety, zoning and public works finals first. Caleed and notified Doug.
|
BLD-Framing/Rough-in | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Mike Jordan
|
|
|
Call 45 mintues to meet // Doug Phone #: ###-####. All issues resolved. ok to sheet rock.
|
BLD-Energy code compliance | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Mike Jordan
|
|
|
Call 45 mintues to meet // Doug Phone #: ###-####
|
BLD-Framing/Rough-in | 12/28/2016 | 12/28/2016 | 12/28/2016 | P | PART |
Mike Jordan
|
|
|
Doug// please call ahead Phone #: ###-####. Instaal the missing h2.5's. Instaal the draft stop. Ok to insulate.
|
BLD-Framing/Rough-in | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | CANC |
Mike Jordan
|
|
|
Doug Phone #: ###-####
|
BLD-Wall Bracing | 9/21/2016 | 9/21/2016 | 9/21/2016 | P | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Interior wall bracing and remainder of exterior. ok to cover exteior.
|
BLD-Framing/Rough-in | 9/7/2016 | 9/8/2016 | 9/8/2016 | A | CANC |
Mike Jordan
|
|
|
doug Phone #: ###-####
|
BLD-Wall Bracing | 9/8/2016 | 9/8/2016 | 9/8/2016 | A | PASS |
Mike Jordan
|
|
|
doug Phone #: ###-####
|
BLD-Foundation | 8/1/2016 | 8/2/2016 | 8/2/2016 | P | PASS |
Mike Jordan
|
|
|
Shawn Phone #: ###-####
|
BLD-Footing | 7/29/2016 | 8/1/2016 | 8/1/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-####
|
BLD-Conference | 7/25/2016 | 7/26/2016 | 7/26/2016 | A | DONE |
Mike Jordan
|
|
|
Reviewed footing and foundation plan and awnsered questions regarding interior column pad footings and thickend slab footings.
|
Print Occupancy Form | | | 7/19/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/19/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/18/2016 | | |
|
|
|
|
Plan assigned to (TLW) | 6/14/2016 | | 7/18/2016 | | PASS |
Tim L. Woodard
|
|
|
1st review completed
|
Routing Off Site - STRUCTURAL | 7/18/2016 | | 7/18/2016 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2016 | | DONE |
Christina Prado
|
|
|
Need RP, GC Form & Revised Certificate of Value for issuance
|
Routing Off Site - STRUCTURAL | 7/15/2016 | | 7/15/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 7/11/2016 | 7/11/2016 | 7/12/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Route to Impact Fee Review | 7/9/2016 | 7/12/2016 | 7/11/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Drainage | 7/11/2016 | | 7/11/2016 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 7/8/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/14/2016 | | 7/8/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/14/2016 | | 7/8/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Meeting | | | 6/29/2016 | | DONE |
|
|
|
Permanent Operation and Maintenance. Taken to Brian Murphy
|
Routing - PLANNING Land Div | 6/14/2016 | | 6/17/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLUMBING | 6/14/2016 | | 6/17/2016 | | PASS |
Daryl Spivey
|
|
|
minor plumbing for storage building
|
Routing - PLANNING | 6/14/2016 | | 6/16/2016 | | PASS |
Leon Letson
|
|
|
|
Routing - MECHANICAL | 6/14/2016 | | 6/16/2016 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 6/14/2016 | | 6/15/2016 | | PASS |
Andy J. Long
|
|
|
General permit issued. Non-commercial/non-residential. Low risk site within large flat church campus. Need to designate valid RP or assign facility manager/applicant.
|
Routing - FIRE | 6/14/2016 | 6/14/2016 | 6/14/2016 | | FAIL |
Katie Marron
|
|
|
Comments attached to case and emailed to architect.
|
Routing - Addressing | 6/14/2016 | | 6/14/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/14/2016 | | 6/14/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Drainage | 6/14/2016 | | 6/14/2016 | | FAIL |
Brian Murphy
|
|
|
NEEDS DRAINAGE PLAN LETTERECT
|
Intake Approval | | | 6/14/2016 | | PASS |
|
|
|
|
Pending Assignment by TLW | 6/14/2016 | | 6/14/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 5/23/2016 | | FAIL |
Javier Guzman
|
|
|
Please provide the following: (Incomplete submittals will not be accepted.)
• Electrical plans are required for new buildings to show: Power plan, Electrical fixture and/or equipment schedule, Panel load schedules and summary of electrical load calculations, one line diagram with details of service, grounding, feeders, transformers and sub-panels, Electrical details/notes, conduit sizes/types, conductor sizes/types, insulation types, circuit wiring sizes/types, homeruns, etc…
|
Application received | | | 5/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 3 2016 5:53AM
|
Intake Approval | | | 5/3/2016 | | FAIL |
Javier Guzman
|
|
|
Please provide the following: (Incomplete submittals will not be accepted.)
• Checklist (#502) must be completed by the project’s Idaho-licensed design professional of record and uploaded with the plans and documents
• The checklist is not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed.
• Upload any addition plans and documents required from the checklist
|