Second Notice | | 12/22/2016 | 2/9/2017 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
First Notice | 12/7/2016 | 12/7/2016 | 12/12/2016 | | DONE |
Candy A. Nichols
|
|
|
mailed 12-13-16
|
BLD-Final | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PASS |
Jim Storey
|
|
|
would like call ahead; randy Phone #: ###-####
|
DOC - Permit Finaled | 12/7/2016 | 12/7/2016 | 12/7/2016 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 11/17/2016 | 11/17/2016 | 11/17/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
|
Issue PAID IN FULL permit | | | 6/17/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/17/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/4/2016 | 5/4/2016 | 5/17/2016 | | PASS |
Javier Guzman
|
|
|
5/17 L2 St. Lukes Central Lab Paper
|
Routing - PLAN CHECK | | | 5/17/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 5/17/2016 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 5/17/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/17/2016 | | DONE |
Christina Prado
|
|
|
All requirements met 5/18/16 ///C_P
Need GC and Revised Cert of Value
|
Inspection Record Card- Bld | | | 5/17/2016 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2016 | | DONE |
|
|
|
called Steve Turney to let know permit is ready-we need GC and rev cert of val
|
Routing - FIRE | 5/13/2016 | 5/5/2016 | 5/13/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 5/5/2016 | | 5/13/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | | | 5/10/2016 | | PASS |
|
|
|
per plans and ISPC
|
Routing - Addressing | 5/5/2016 | | 5/5/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/5/2016 | | 5/5/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/4/2016 | | DONE |
|
|
|
|
Intake Approval | | | 5/4/2016 | | PASS |
|
|
|
as per Javier Guzman
|
Recd Pcfee & Taken To Pln CK | | | 5/4/2016 | | DONE |
|
|
|
|
Application received | | 5/3/2016 | | | |
|
|
|
|