Letter of compliance/Occupancy | | | 1/3/2017 | | DONE |
|
|
|
|
BLD-Final | 11/28/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Tony Young
|
|
|
Call for access Phone #: 6089669 >> Inspection requested via mobile web by Nate///415
|
DOC - Permit Finaled | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 11/23/2016 | 11/28/2016 | 11/28/2016 | A | PASS |
Tony Young
|
|
|
Call for access Phone #: 6089669 >> Inspection requested via mobile web by Nate,, all ok,, just needs address posted
|
BLD-Energy code compliance | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | PASS |
Tony Young
|
|
|
As early as possible Phone #: 6089669 >> Inspection requested via mobile web by Nate
|
BLD-Framing/Rough-in | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | PASS |
Tony Young
|
|
|
Phone #: 6089669 >> Inspection requested via mobile web by Nate,, ok to insulate
|
BLD-Wall Bracing | 8/16/2016 | 8/16/2016 | 8/16/2016 | P | PASS |
Tony Young
|
|
|
Phone #: 6089669 >> Inspection requested via mobile web by Nate
|
BLD-Framing/Rough-in | 8/15/2016 | 8/16/2016 | 8/16/2016 | A | NR |
Tony Young
|
|
|
Phone #: 6089669 >> Inspection requested via mobile web by ,,,, walk through,, made notes on truss plan,, need energy seal pack
|
BLD-Foundation | 7/12/2016 | 7/12/2016 | 7/12/2016 | P | DONE |
Tony Young
|
|
|
Dane Phone #: ###-####
|
OVERRIDE | | | 7/12/2016 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/12/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/12/2016 | | DONE |
|
|
|
as per Brian McGowen, no fees due
|
BLD-Footing | 7/8/2016 | 7/11/2016 | 7/11/2016 | P | PASS |
Tony Young
|
|
|
Dane Phone #: ###-####
|
Routing Walk-In (BLD) | 7/11/2016 | 7/11/2016 | 7/11/2016 | A | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 7/11/2016 | | 7/11/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLANNING | 7/11/2016 | | 7/11/2016 | | PASS |
Colleen T Carroll
|
|
|
Revised Site Plan
|
BLD-Footing | 7/7/2016 | 7/8/2016 | 7/9/2016 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/27/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/27/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/9/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
OVERRIDE | | | 6/8/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 5/12/2016 | 5/12/2016 | 6/8/2016 | | DONE |
Brian McGowan
|
|
|
due 5/25 - Failed 5/25-16- Planning failed, beams by others failed, wall bracing issues.
|
Routing - PLAN CHECK | 6/8/2016 | | 6/8/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/8/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/8/2016 | | DONE |
|
|
|
Need a letter from ACHD stating if fees are needed or not
|
Inspection Record Card- Bld | | | 6/8/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/7/2016 | | DONE |
|
|
|
resubmittals recieved 4 wall bracing and 2 sets of sheets 6 of 7 & 7 of 7-took to Brian McGowan
|
Routing - PLANNING | 6/1/2016 | | 6/1/2016 | | PASS |
Colleen T Carroll
|
|
|
Per Planning approval existing home to be demoed prior to final inspection of new home. Setbacks OK per H.S.
|
1st review completed | | | 5/25/2016 | | FAIL |
Brian McGowan
|
|
|
Site plan needs to be resubmitted meetiong Zoning Specifications.
Wall bracing needs to have BWL noted on the plan.
All beams and headers must be noted: beam by others is not acceptable.
|
Routing - PLAN CHECK | 5/16/2016 | | 5/25/2016 | | FAIL |
Brian McGowan
|
|
|
Site plan needs to be resubmitted meetiong Zoning Specifications.
Wall bracing needs to have BWL noted on the plan.
All beams and headers must be noted: beam by others is not acceptable.
|
Routing - MECHANICAL | 5/11/2016 | | 5/16/2016 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 5/11/2016 | | 5/12/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - Addressing | 5/11/2016 | | 5/11/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 5/11/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/11/2016 | | DONE |
|
|
|
|
Intake Approval | | | 5/11/2016 | | PASS |
|
|
|
planning has approved the intake with conditions as per Hal Simmons
|
Recd Pcfee & Taken To Pln CK | | | 5/11/2016 | | DONE |
|
|
|
|
Intake Approval | | | 5/5/2016 | | FAIL |
|
|
|
checking back with customer about building a new house with the current house still existing. possible planning approval needed prior to intake.
|
Application received | | 5/4/2016 | | | |
|
|
|
|
Routing - PLANNING | 5/11/2016 | | | | FAIL |
|
|
|
See setback requirements in the Sycamore District 5/11/16
|