First Notice | 6/9/2017 | 6/9/2017 | 6/14/2017 | | DONE |
Brandon Shaw
|
|
|
This permit finaled on the web by Kim Anderson
|
BLD-Final | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kaleb Checketts
|
DOC - Permit Finaled | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Brandon Shaw
|
|
|
|
Issue PAID IN FULL permit | | | 7/18/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/6/2016 | 5/6/2016 | 7/12/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 5/19 L2 Verizon BOI CHICKADEE, tower, generator and pad ePlan
|
Routing - PLAN CHECK | 7/12/2016 | | 7/12/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/12/2016 | | DONE |
|
|
|
***MET 7-18-16 CAN***need GC and rev cert of val
|
Routing - PLANNING | 5/6/2016 | | 5/18/2016 | | PASS |
Ted Vanegas
|
|
|
|
1st review completed | | | 5/18/2016 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - PLAN CHECK | 5/6/2016 | | 5/18/2016 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - Erosion and Sediment | 5/6/2016 | | 5/12/2016 | | PASS |
Andy J. Long
|
|
|
No ESC plan needed, minimal earth disturbance within existing tower area
|
Routing - FIRE | 5/6/2016 | 5/6/2016 | 5/6/2016 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Intake Approval | | | 5/6/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 5/6/2016 | | 5/6/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2016 | | 5/6/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 5/5/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 5 2016 9:14AM
|