Permit Information
Permit NumberBLD16-01567
StatusFinaled
Name DARREN S LLOYD
Site Address 1961 S BROADWAY AVE
Project NameBoise Physical Therepy
Customer Number 
ePlanReviewYes
Description
(BOISE PHYSICAL THERAPY) Permit for interior renovations to an existing building with work to include the removal of some interior nonbearing walls, reconfiguration of some existing trusses, installation of two new beams and an additional footing as well as related interior finishes per the approved plans and tne attached engineering. This building is not fire sprinklered. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 12/18/20161/11/2017 DONE
Third Notice 11/26/201612/13/2016 DONE
sent with a letter
Third Notice 10/15/201611/21/2016 DONE
Third Notice 9/24/201610/10/2016 DONE
Second Notice 8/22/20169/19/2016 DONE
First Notice 8/8/20168/12/2016 DONE
Mailed 8-15-16
Permanent Occupancy  7/29/2016 DONE
BLD-Final7/27/20167/28/20167/28/2016PPASS
DetailsJim Storey
Darren Phone #: ###-####
FIRE-Final Inspection7/27/20167/28/20167/28/2016APASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Noted that the general contractor was informed about the thumbturn deadbolts need to be changed, allowed one double keyed deadbolt and single action paddle type door hardware on other exterior door. Final life fire safety inspection passed/complete.
BLD-Energy code compliance7/14/20167/15/20167/15/2016PPASS
DetailsJim Storey
Insulation // Darren Phone #: ###-####
BLD-Framing/Rough-in7/11/20167/14/20167/14/2016PPART
DetailsJim Storey
Darren Phone #: ###-#### need engineering and form up footting 36x36
Permit Ready to Issue  7/6/2016 DONE
DetailsChristina Prado
Need GC Form & Revised certificate of value for issuance
Issue PAID IN FULL permit  7/6/2016 DONE
Print Occupancy Form  7/6/2016 DONE
Plan assigned to (CDM)6/7/20166/7/20167/5/2016 PASS
DetailsCarl D Madsen
First review completed. Level 3 TI - ePlanReview - Boise Physical Therapy
Routing - PLAN CHECK7/5/2016 7/5/2016 PASS
DetailsCarl D Madsen
Plan review report attached.
PLANS/APPL TAKEN TO FRONT DESK  7/5/2016 DONE
Routing Off Site - STRUCTURAL6/30/2016 6/30/2016 PASS
DetailsAdele J Schaffeld-Griffin
signed off in e plan
Routing - PLAN CHECK6/28/2016 6/28/2016 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK6/24/2016 6/24/2016 FAIL
DetailsCarl D Madsen
No new plans or response letter has been provided and none of the review comments have been addressed.
1st review completed  6/21/2016 FAIL
Routing Off Site - STRUCTURAL6/7/2016 6/21/2016 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK6/7/2016 6/21/2016 FAIL
DetailsCarl D Madsen
Additional information requested.
Routing - FIRE6/7/20166/7/20166/9/2016 PASS
DetailsKatie Marron
Plans reviewed, basic life safety requiremens apply. No additional comments required.
Routing - Design Review6/7/2016 6/9/2016 PASS
DetailsSarah Schafer
Sarah Schafer
Routing - MECHANICAL6/7/2016 6/8/2016 PASS
DetailsTroy James
Routing - Addressing6/7/2016 6/7/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS6/7/2016 6/7/2016 PASS
DetailsRachael Beierle
Intake Approval  6/3/2016 PASS
DetailsJason Blais
Prescreen approved by Carl Madsen and plan review fees paid.
Intake Approval  5/24/2016 FAIL
Original pre-screen
Complete the form 520 checklist and provide all required items.
The plans indicate modifications to the roof system and engineering is required.
5/24/16
Please complete the 520 checklist.
Engineering is required to be stamped by a licensed structural engineer. Seismic, gravity and lateral loads are required to be addressed as part of the structural calculations.
Please upload the mechanical sheets individually as required and not in a packet
Wrighsoft is a house software program and not a commercial building calculation software.
Please provide the correct naming convention for all plan sheets.
Exterior changes are being made to the structure and require planning approval prior to submittal.
Intake Approval  5/6/2016 FAIL
Application received  5/5/2016 DONE
Application submitted via PDS Online on May 5 2016 10:04AM
Pending Assignment by JCB6/7/2016    
DetailsJason Blais