BLD-Final | 9/19/2016 | 9/20/2016 | 9/27/2016 | A | DONE |
Dave Hannah
|
|
|
would like call ahead; jim Phone #: ###-####
|
BLD-Final | 9/27/2016 | 9/27/2016 | 9/27/2016 | P | PASS |
Dave Hannah
|
|
|
would like call ahead; Jim Phone #: ###-####
|
DOC - Permit Finaled | 9/27/2016 | 9/27/2016 | 9/27/2016 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 9/20/2016 | 9/20/2016 | 9/20/2016 | | PASS |
Ted Vanegas
|
|
|
|
BLD-Other | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | PEND |
Dave Hannah
|
|
|
Jim//inspection for the stairs Phone #: ###-####
|
BLD-Conference | 8/16/2016 | 8/16/2016 | 8/16/2016 | P | DONE |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Energy code compliance | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 7/18/2016 | 7/19/2016 | 7/19/2016 | A | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
Plan assigned to (BJM) | 6/7/2016 | 6/7/2016 | 6/14/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/7/2016 | | 6/14/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/14/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/14/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/14/2016 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Bld | | | 6/14/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/14/2016 | | DONE |
|
|
|
Left a message for Josh informing him that this permit is ready and the fee amount due for issuance
|
Issue PAID IN FULL permit | | | 6/14/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/7/2016 | | DONE |
|
|
|
resubmittals turned in
|
Routing - PLAN CHECK | 6/3/2016 | | 6/3/2016 | | FAIL |
Brian McGowan
|
|
|
Revised structural engineering drawings were not part of the resubmittals. No information on the covered back porch was provided.
|
Plan resubmittals received | | | 5/23/2016 | | DONE |
|
|
|
One copy of sheets S-2, A-1 through A-18. Taken to Brain Mc
|
Routing Walk-In (BLD) | 5/10/2016 | 5/10/2016 | 5/10/2016 | A | FAIL |
Brian McGowan
|
|
|
Missing (2) Engineering sheets. Proposed stairs are not compliant with winder stairs or typical stairs. Missing sections thru proposed dormers to show adequate head height.
|
1st review completed | | | 5/10/2016 | | FAIL |
Brian McGowan
|
|
|
Missing (2) Engineering sheets. Proposed stairs are not compliant with winder stairs or typical stairs. Missing sections thru proposed dormers to show adequate head height.
|
Routing - PLAN CHECK | 5/10/2016 | | 5/10/2016 | | FAIL |
Brian McGowan
|
|
|
Missing (2) Engineering sheets. Proposed stairs are not compliant with winder stairs or typical stairs. Missing sections thru proposed dormers to show adequate head height.
|
Routing Walk-In (Zoning) | 5/9/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Matthew A Halitsky
|
|
|
DRH15-00328
|
Application received | | 5/9/2016 | | | |
|
|
|
|