First Notice | | 2/16/2017 | 3/10/2017 | | DONE |
|
|
|
sent in mail 3-13-17
|
Permanent Occupancy | | | 2/6/2017 | | DONE |
|
|
|
|
BLD-Final | 2/2/2017 | 2/3/2017 | 2/3/2017 | P | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-####
|
FIRE-Final Inspection | 2/2/2017 | 2/3/2017 | 2/3/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for this permit passed/complete.
|
PubWorks Occupancy Approval | 1/19/2017 | 1/19/2017 | 1/19/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 1/13/2017 | 1/13/2017 | 1/13/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 11/30/2016 | 11/30/2016 | 11/30/2016 | | PASS |
Jim Storey
|
|
|
|
BLD-Foundation | 7/19/2016 | 7/19/2016 | 7/19/2016 | P | PASS |
Jim Storey
|
|
|
Manuel Phone #: ###-####si
|
BLD-Footing | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Jim Storey
|
|
|
Manual-BLDG A Phone #: ###-#### si
|
Place hold on job | 7/11/2016 | | 7/12/2016 | | DONE |
Carlos Velazquez
|
|
|
DO NOT ISSUE WITHOUT BLD16-01515, BLD16-01652 TO BLD16-01655 AND BLD16-01691
|
Issue PAID IN FULL permit | | | 7/12/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/12/2016 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 5/18/2016 | 5/18/2016 | 7/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Building A
|
Routing Off Site - STRUCTURAL | 7/11/2016 | | 7/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 7/11/2016 | | 7/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/11/2016 | | DONE |
|
|
|
***all requirments met 7-12-16 /CEV
Need ACHD, RP, GC Form and Revised Cert of Value
|
Route to Impact Fee Review | 6/8/2016 | 6/11/2016 | 6/10/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 5/18/2016 | | 6/8/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 6/8/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 5/18/2016 | | 6/8/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 6/2/2016 | | 6/2/2016 | | PASS |
Katie Marron
|
|
|
Report attached to case.
|
Routing PW Sewer Design | 5/18/2016 | | 5/20/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - Addressing | 5/18/2016 | | 5/19/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2016 | | 5/18/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 5/18/2016 | | 5/18/2016 | | PASS |
Andrea Tuning
|
|
|
|
Pending Assignment by TLW | 5/18/2016 | | 5/18/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 5/13/2016 | | PASS |
|
|
|
|
Application received | | 5/10/2016 | | | |
|
|
|
|
Application received | | 5/10/2016 | | | |
|
|
|
|