BLD-Final | 12/30/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Jim Storey
|
|
|
Jeremy Phone #: ###-####
|
DOC - Permit Finaled | 12/30/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 12/22/2016 | 12/23/2016 | 12/23/2016 | A | FAIL |
Jim Storey
|
|
|
Buster Phone #: ###-#### saftey glazzing in all cabnet doors/ charge closers in garages
|
BLD-Energy code compliance | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | PASS |
Phil Shearer
|
|
|
Buster Phone #: ###-####
|
Plan Modification Accepted | | | 10/4/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 10/4/2016 | | 10/4/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Framing/Rough-in | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PART |
Jim Sly
|
|
|
Buster Phone #: ###-#### All framing OK except......Need fireblock above fireplace.
|
BLD-Wall Bracing | 8/22/2016 | 8/22/2016 | 8/22/2016 | P | PASS |
Jim Storey
|
|
|
Buster Phone #: ###-####
|
BLD-Foundation | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-####
|
BLD-Footing | 6/28/2016 | 6/29/2016 | 6/29/2016 | A | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
PubWorks Subgrade Approval | 6/28/2016 | 6/28/2016 | 6/28/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Plan assigned to (LEG) Tisha | 5/26/2016 | | 6/23/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 6/1 L2 hillside; plan review report
|
OVERRIDE | | | 6/22/2016 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/22/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/22/2016 | | DONE |
|
|
|
notified customer that permit was ready
|
Issue PAID IN FULL permit | | | 6/22/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/22/2016 | | 6/22/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/22/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/22/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/20/2016 | | DONE |
|
|
|
resubmittal received 2 sets of sheets of 1-10 and 2 sets of lateral calcs & 2 sets of foundation calcs-took to Brian McGowan
|
Routing - PLAN CHECK | 6/16/2016 | | 6/16/2016 | | FAIL |
Tisha Gallop
|
|
|
need to show prescriptive wall bracing compliance with unengeered portion of building; spoke with Steve from RamTech (designer) on phone about corrections.
|
Routing - PLANNING | 6/15/2016 | | 6/15/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Plan resubmittals received | | | 6/14/2016 | | DONE |
|
|
|
received two complete sets of plans- put on Tisha's desk
|
1st review completed | | | 6/1/2016 | | FAIL |
|
|
|
pending approval by plan check
|
Routing - PLAN CHECK | 5/23/2016 | | 6/1/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - FIRE | 5/20/2016 | 5/20/2016 | 5/23/2016 | | PASS |
Scott Arellano
|
|
|
No comments attached to plans. However, this structure is subject to Fire Department inspection for compliance with BMC 7-01-69 section 4920 as relates to Defensible Space from undeveloped land.
|
Routing - Erosion and Sediment | 5/19/2016 | | 5/20/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Permit for the construction of a new 3,800 sq. ft., one story single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately *** sq. ft. of covered patio/porch and a *** sq. ft. attached garage
|
Routing - MECHANICAL | 5/19/2016 | | 5/19/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/16/2016 | | 5/17/2016 | | FAIL |
Sue Cummings
|
|
|
Needs ADU approval for the "casita"
|
Routing - PUBLIC WORKS | 5/13/2016 | | 5/16/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Grading-Hillside | 5/13/2016 | | 5/16/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing PW Sewer Rating | 5/13/2016 | | 5/13/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 5/13/2016 | | 5/13/2016 | | PASS |
Laura Hunter
|
|
|
|
Application received | | 5/12/2016 | | | |
|
|
|
|