BLD-Final | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | PASS |
Jim Sly
|
|
|
Bill Phone #: ###-####
|
DOC - Permit Finaled | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 12/19/2016 | 12/20/2016 | 12/20/2016 | P | PEND |
Jim Sly
|
|
|
bill Phone #: ###-#### Looked at footing. pressure treated window jamb. engineering from MTI showing rebar Etc Meets Hillside Ord. OK to final when gravel and trim installed.
|
CHANGE STATUS TO (ISS) | | | 12/19/2016 | | DONE |
|
|
|
plan mod fees paid
|
Plan assigned to (BJM) | 6/7/2016 | 6/7/2016 | 12/16/2016 | | DONE |
Brian McGowan
|
|
|
Failed Hillside. Needs forensic inspection.
As per Jason Taylor, window well is a retaining wall and needs to meet Hillside requirements as such. Contractor had finished the wall with no engineering or proof of rebar installation to meet code. Proof of code compliance must be provided.
|
Routing - PLAN CHECK | | | 12/16/2016 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 12/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 12/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 12/16/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/16/2016 | | DONE |
|
|
|
|
Telephone call | | | 12/16/2016 | | DONE |
|
|
|
called Tony to let know permit is ready
|
Routing PW Grading-Hillside | 12/5/2016 | | 12/6/2016 | | PASS |
Jason C. Taylor
|
|
|
Recieved engineers approval of subgrade. JCT
|
Plan resubmittals received | | | 12/5/2016 | | DONE |
|
|
|
received three copies of inspection report- looked for original plans and couldn't find them-gave to JCT
|
Routing Walk-In (PW Hillside) | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | FAIL |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
1st review completed | | | 6/13/2016 | | FAIL |
Brian McGowan
|
|
|
See Hillside for specific reasons of not passing
|
Routing - PLAN CHECK | 6/7/2016 | | 6/13/2016 | | FAIL |
Brian McGowan
|
|
|
See PW-Hillside.
|
Plan Modification Accepted | | | 6/7/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/16/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/16/2016 | | DONE |
|
|
|
This permit was created on the web by Bill Judy
|