Print Statement | | | 11/23/2018 | | DONE |
|
|
|
sent 1st late notice
|
Print Statement | | | 8/14/2018 | | DONE |
|
|
|
|
Third Notice | | 7/16/2018 | 8/7/2018 | | DONE |
|
|
|
mailed 7-10-18
|
Second Notice | | 6/21/2018 | 7/11/2018 | | DONE |
|
|
|
mailed 7-12-18
|
First Notice | | 5/25/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Permanent Occupancy | | | 5/15/2018 | | DONE |
|
|
|
|
BLD-Final | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. All issues have been resolved. Ok for perm. occ.
|
BLD-Framing/Rough-in | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | CANC |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Final | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. All issues have been resolved except for protection of sleeves in 1hr. roof/ceiling assembly above coolers.
|
Temporary Occupancy | 4/19/2018 | 7/18/2018 | 4/19/2018 | | DONE |
Tisha Gallop
|
|
|
Permanent certificate of occupancy pending approval by structural.
|
BLD-Conference | 4/4/2018 | 4/4/2018 | 4/4/2018 | A | DONE |
Mike Jordan
|
|
|
Request for Michael Jordan to visit the job site to discuss outstanding items. Phone #: ###-#### Inspection requested via web by Steve Jacobsen. Discussed 3M duct wrap EJ with contractor on wrapping the solar light tubes and duct for med gas room ventilation. Noted to contractor to send EJ to building official for approval.
|
FIRE-Final Inspection | 3/9/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Jim Page
|
|
|
Delayed egress doors tested and verified for proper operation. Final life fire safety inspection complete.
|
Zoning Approval | 3/1/2018 | 3/1/2018 | 3/1/2018 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PART |
Mike Jordan
|
|
|
Ok for temp occupancy only.
|
BLD-Framing/Rough-in | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Bldg #100 Missing fire dampers at 1hr ceiling at rooms 117 and 126. Rooms 148 and 150 need 45 min doors., protec penetrations at 1hr. ceiling above coolors. provide 1hr. shaft in attic for gas room ventilation in room 131. Also noted solar light tubes installed in conferance room, not on approved plans. Architect to provide details on how to protect the opening in the 1hr. ceiling assembly. Will be ok for temp occ. once a bond has been posted for zoning to allow the state to start conducting their inspections and for building owner to move furniture in ONLY.
|
FIRE-Final Inspection | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PART |
Troy Cobbley
|
|
|
A temporary for the life safety is being given to provide access for State Of Idaho certification. If cooking or training is to be started Scott Arellano is to be contacted for approval. For a final sign off I need the delayed egress doors tested, the project related fire alarm permit finaled and the exit discharge lighting issues approved as discussed.
Steve Phone #: ###-####
|
BLD-Final | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | FAIL |
Mike Jordan
|
|
|
did not want to schedule fire life & safety and understood fir permit failed inspection /// Nathan Phone #: ###-####. Bldg #300. Doors 302,303,304 to be 45 min. with self closer and smoke seals. Protect through penetrations in data room 322. No fire dampers in ceilings in rooms 307, 310 and 325. Bldg 200, doors at rooms 211, 212 and 213 to be 45 min., self closing with smoke seals and sweeps.
|
BLD-Final | 2/20/2018 | 2/21/2018 | 2/21/2018 | A | FAIL |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Bldg 200 only walk through. Needs to install all mirrors. Doors 204,210, 226 and 211 are required to be min. 45 min rated, they are not. Also need to verify slopes on sides to bldg 200, west side.
|
FIRE-Final Inspection | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the exit discharge lighting issue resolved, need to test the Delay Egress Doors, need smoke damper actuation tested and shown on the fire alarm plans. See the mechanical sheets for locations of the fire/smoke dampers.
|
FIRE-Alarm Testing | 2/19/2018 | 2/21/2018 | 2/21/2018 | A | CANC |
Troy Cobbley
|
|
|
continued phased inspection of alarms Phone #: ###-#### Inspection requested via web by Steve Jacobsen
|
Meeting | | | 2/21/2018 | | DONE |
Scott Arellano
|
|
|
Met with life safety field inspector to discuss Fire Smoke Damper installation in building sections 200 & 300. Informed all inspection personnel and mechanical contractor of the 9 F/S dampers to be installed. Fire Alarm subcontractor has also been contacted.
|
FIRE-Alarm Testing | 2/19/2018 | 2/20/2018 | 2/20/2018 | A | CANC |
Troy Cobbley
|
|
|
continued phased inspection of alarms Phone #: ###-#### Inspection requested via web by Steve Jacobsen
|
PubWorks Occupancy Approval | 2/14/2018 | 2/14/2018 | 2/14/2018 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 2/9/2018 | 2/12/2018 | 2/12/2018 | A | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final yet. Todays inspection was just to verify that the exit signs, emergency lights and exit discharge lights functioned on emergency generator. I noted that the exit discharge lights have been connected to photo cells for control. I have contacted plan review since I do not see this allowed in the Code.
Steve Phone #: ###-####
|
FIRE-Conference | 1/29/2018 | 1/29/2018 | 1/30/2018 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with Steve which included the medical gas rooms. Per the electrician the exit discharge lights are controled by a photo cell. Per Chapter 10 of the IFC no allowance is made for this or timers.
Steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Building #300.
|
BLD-Ceiling Grid Inspection | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | PASS |
Mike Jordan
|
|
|
Nate Phone #: ###-####. Building 100 ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 | A | PASS |
Mike Jordan
|
|
|
Building 200 ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Wrong inspection entered. rescheduled.
|
BLD-Ceiling Grid Inspection | 11/16/2017 | 11/16/2017 | 11/17/2017 | P | CANC |
Mike Jordan
|
|
|
building 200- Steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Mike Jordan
|
|
|
ceiling grid in bldg. 200 ok.
|
BLD-Framing/Rough-in | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. south half of building 300 ok to sheet rock.
|
BLD-Framing/Rough-in | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. north rooms and lid ok to sheet rock.
|
BLD-Framing/Rough-in | 10/6/2017 | 10/9/2017 | 10/9/2017 | A | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Energy code inspection, exterior walls bldg. #300.
|
BLD-Framing/Rough-in | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Framing for p.c.
|
BLD-Framing/Rough-in | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Exterior walls only ok, pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Ok to rock corridors ceilings and wall to plate line only. Also spoke to contractor about the possibilty of insulating that portion of wall above plate line prior to sheet rock.
|
BLD-Framing/Rough-in | 9/8/2017 | 9/11/2017 | 9/11/2017 | A | PART |
Dave Hannah
|
|
|
Nathan Phone #: ###-#### ok to cover walls bldg 100
|
BLD-Framing/Rough-in | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Ok to rock remaining lids in bldg 100. Work in progress on insulation.
|
BLD-Energy code compliance | 8/29/2017 | 8/29/2017 | 8/29/2017 | P | CANC |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 8/29/2017 | 8/29/2017 | 8/29/2017 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. building 100, ok to insualte north of first corridor only.
|
BLD-Framing/Rough-in | 8/25/2017 | 8/28/2017 | 8/28/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Building 100 framing. Needs to complete airseal, complete all pre rock and fireblocking nd install all hatchannel.
|
BLD-Framing/Rough-in | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Exterior shear on bldg 300 is now ok.
|
BLD-Framing/Rough-in | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. North wing, bldg 200 ok. Wall bracing on bldg. 300 noted several areas missing blocking and fasteners.
|
BLD-Conference | 8/8/2017 | 8/9/2017 | 8/9/2017 | A | FAIL |
Mike Jordan
|
|
|
Remove sheet rock from furred walls, nrth wing of building 200. Remove tyvek from exteriorof building 300 for bracing inspection. The tenmat listing provided for light protection in th 1 hr. ceiling is non compliant for this use. A corection notice was issued.
|
BLD-Framing/Rough-in | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Ok to sheetrock corridor ceilings in bldg. 100. only.
|
BLD-Framing/Rough-in | 7/24/2017 | 7/25/2017 | 7/25/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior shear and inteior shear walls on bldg. 100 ok. Smoke barrier above grid in bldg. 200 ok and at concealed areas. Roof ceiling assembly in concealed areas ok as well.
|
BLD-Energy code compliance | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Elelctrical room Bldg. 100 ok.
|
BLD-Framing/Rough-in | 7/21/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Mike Jordan
|
|
|
Bldg. 100 roof ok toover.
|
BLD-Framing/Rough-in | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | FAIL |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Complete all penetrations on smoke barrier wall. Remove rock from areas behind tubs on either side of smoke barrier walls and conplete ceiling assembly and rock those portions of smoke barrier.
|
BLD-Framing/Rough-in | 7/14/2017 | 7/14/2017 | 7/17/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Bldg 200 ok to sheet rock except for north wing.
|
BLD-Conference | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | CANC |
Mike Jordan
|
|
|
Steve Jacobson Phone #: ###-####
|
BLD-Energy code compliance | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Jacobson Phone #: ###-####. South and west exterior walls only on bldg.200 ok.
|
BLD-Framing/Rough-in | 7/12/2017 | 7/12/2017 | 7/12/2017 | A | PASS |
Mike Jordan
|
|
|
Bldg. 100 roof strapping was completed. Prevously noted missing straps not required per engineers site visit. South and west wings rooms ok.
|
BLD-Framing/Rough-in | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | PART |
Mike Jordan
|
|
|
Roof nailing ok. Installing strapping when on site. Engineer to provide RFI for alternate connections on drag trusses.
|
BLD-Framing/Rough-in | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | NR |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Roof for building 100, not ready.
|
BLD-Framing/Rough-in | 6/8/2017 | 6/9/2017 | 6/9/2017 | A | PART |
Dave Hannah
|
|
|
Steve Phone #: ###-#### south side of bldg 200 corradors ok to cover lids
|
BLD-Conference | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | DONE |
Mike Jordan
|
|
|
Reviewed alternate 1hr. details from architect for double walls to comply with the 1hr. wall requirements. Listed Assembly provided with addition of 2 layers of 5/8 type x rock above double top plates to keep continuity of 1hr. ceiling assembly.
|
BLD-Conference | 6/5/2017 | 6/5/2017 | 6/5/2017 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Conference | 6/1/2017 | 6/2/2017 | 6/2/2017 | A | DONE |
Mike Jordan
|
|
|
Meeting with sub contractors on fire stopping requirements.
|
BLD-Wall Bracing | 5/22/2017 | 5/25/2017 | 5/25/2017 | A | PASS |
Mike Jordan
|
|
|
Bldg. 200 exterior shearwalls ok.
|
BLD-Framing/Rough-in | 5/19/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Mike Jordan
|
|
|
Bldg. 200 roof nailing ok. all straps in and completed. Also received RFI from engineer of record giving staple conversion for roof sheathing attachment.
|
BLD-Wall Bracing | 5/22/2017 | 5/22/2017 | 5/22/2017 | A | FAIL |
Mike Jordan
|
|
|
Bldg. 200 exterior shear walls. Several areas missed. All missed areas were marked. Framer to fasten all missed areas.
|
BLD-Framing/Rough-in | 5/19/2017 | 5/19/2017 | 5/19/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PEND |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Roof nailing on bldg. 200. Used staples, plans call for 8d nails. Waiting for RFI from engineer.
|
(F) Reprint permit | | | 4/24/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/24/2017 | | DONE |
|
|
|
Plan Mod
|
Telephone call | | | 4/19/2017 | | DONE |
|
|
|
customer called for inspection but plan mod fees are due and have been due since 1/18/17-i told him berore and inspection can be done they need to come in and pick up plan mod
|
OVERRIDE | | | 1/18/2017 | | |
|
|
|
|
Plan assigned to (CJW) | 1/6/2017 | 1/6/2017 | 1/18/2017 | | PASS |
Carl Westfall
|
|
|
plan mod
|
Routing - PLAN CHECK | 1/6/2017 | | 1/18/2017 | | PASS |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 1/10/2017 | | 1/18/2017 | | PASS |
Carl Westfall
|
|
|
Jordan Terry KPFF
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/18/2017 | | DONE |
|
|
|
DO NOT RE ISSUE. PLAN MOD
|
Plan Modification Accepted | | | 1/6/2017 | | DONE |
Christina Prado
|
|
|
For structural revisions
|
BLD-Foundation | 12/6/2016 | 12/7/2016 | 12/7/2016 | P | PASS |
Mike Jordan
|
|
|
Rebar // Steve Phone #: ###-####. Perimeter stemwalls for bldg. 100.
|
BLD-Footing | 12/1/2016 | 12/1/2016 | 12/1/2016 | P | PART |
Mike Jordan
|
|
|
Steve-rebar Phone #: ###-####. Bldg.300 perimeter footings. Will have special inspection.
|
BLD-Footing | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Perimeter stemwalls and courtyards for bldg. 200. Perimeter footings for blg. 100 and garden area.
|
BLD-Footing | 11/15/2016 | 11/16/2016 | 11/16/2016 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Perimter footings and west courtyard footings for bldg. 200. Will have special inspection..
|
Issue PAID IN FULL permit | | | 10/26/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/26/2016 | | DONE |
|
|
|
|
Expiration Notice | 10/19/2016 | 11/9/2016 | 10/19/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 10/10/2016 | | |
|
|
|
|
Route to Impact Fee Review | 9/8/2016 | 9/11/2016 | 10/10/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CJW) | 8/1/2016 | 8/1/2016 | 10/10/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Aug 18 - 15 days) (Sept 8 - 30 days) St. Al's Skilled Nursing 100 beds
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/10/2016 | | DONE |
Christina Prado
|
|
|
***MET 10-25-16 CAN***NEED ACHD, alll other requirements met
|
Routing - PLAN CHECK | 10/3/2016 | | 10/10/2016 | | PASS |
Carl Westfall
|
|
|
(10-3-16) Waiting for the results of the 3rd structural review.
(10-10-16) Drawings approved
|
Routing Off Site - STRUCTURAL | 10/3/2016 | | 10/7/2016 | | PASS |
Carl Westfall
|
|
|
Jordan Terry KPFF
|
Plan resubmittals received | | | 10/3/2016 | | DONE |
|
|
|
received O&M agreement
|
Plan resubmittals received | | | 10/3/2016 | | DONE |
|
|
|
|
Routing - Design Review | 10/3/2016 | | 10/3/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - C.D.H | 9/20/2016 | | 9/28/2016 | | PASS |
Carl Westfall
|
|
|
Brent Copes has 83709 - send to him
(9-28-16) Called Brent Copes. Left a voice message. Asked him to either pass it or fail it so the workflow can be sent back to the applicant.
|
Routing - PLAN CHECK | 9/19/2016 | | 9/28/2016 | | PEND |
Carl Westfall
|
|
|
Resubmittal review completed on 9-21-16. Waiting for the results of the 2nd structural review.
|
Routing Off Site - STRUCTURAL | 9/20/2016 | | 9/28/2016 | | FAIL |
Carl Westfall
|
|
|
Jordan Terry KPFF
|
Plan resubmittals requested | | | 9/28/2016 | | DONE |
|
|
|
|
Routing - Design Review | 9/20/2016 | | 9/26/2016 | | FAIL |
Andrea Tuning
|
|
|
|
Routing PW Solid Waste | 9/20/2016 | | 9/26/2016 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PLUMBING | 9/20/2016 | | 9/22/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Sewer Design | 9/20/2016 | | 9/22/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - MECHANICAL | 9/20/2016 | | 9/21/2016 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 9/20/2016 | | 9/21/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Plan resubmittals received | | | 9/19/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/8/2016 | | DONE |
|
|
|
|
1st review completed | | | 9/8/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/1/2016 | | 9/8/2016 | | FAIL |
Carl Westfall
|
|
|
1st IBC plan review done
|
Routing - PLANNING Land Div | 8/1/2016 | | 8/31/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Environmental | 8/2/2016 | | 8/18/2016 | | PASS |
Rick Christenson
|
|
|
1500 Gallon Exterior Interceptor Shown
|
Routing Off Site - STRUCTURAL | 8/1/2016 | | 8/16/2016 | | FAIL |
Carl Westfall
|
|
|
Jordan Terry
|
Routing - MECHANICAL | 8/1/2016 | | 8/16/2016 | | FAIL |
Troy James
|
|
|
|
Routing PW Drainage | 8/2/2016 | | 8/12/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 8/2/2016 | | 8/10/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Sewer installed but not yet accepted. Testing still needs to be completed and a letter of acceptance issued by the City prior to permitting connections.
|
Plan assigned to (AJS) | 8/1/2016 | 8/1/2016 | 8/5/2016 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 8/1/2016 | 8/1/2016 | 8/2/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing PW Solid Waste | 8/2/2016 | | 8/2/2016 | | FAIL |
Peter J. McCullough
|
|
|
|
Routing PW Street Lights | 8/2/2016 | | 8/2/2016 | | PASS |
Tom Marshall
|
|
|
Approved with conditions
|
Routing - PUBLIC WORKS | 8/1/2016 | | 8/2/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 8/1/2016 | | 8/2/2016 | | FAIL |
Daryl Spivey
|
|
|
note-- cleanouts required on 2" piping below grade every 50'.
change mark-- provide sizing for the med gas system.
|
Routing - PLANNING | 8/1/2016 | | 8/1/2016 | | PASS |
Cody Riddle
|
|
|
Parcel boundary issue already noted in DRH.
|
Pending Assignment by TLW | 8/1/2016 | | 8/1/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Erosion and Sediment | 8/1/2016 | | 8/1/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and approval required prior to earth disturbance)
100 bed skilled nursing facility
|
Routing - Design Review | 8/1/2016 | | 8/1/2016 | | FAIL |
Andrea Tuning
|
|
|
DRH16-00057 -
Parcel must match property lines proposed. (legal parcel)
Provide 3 bicycle parking spaces.
Widen planter island in northeast corner of the site to be 8-feet in width.
|
Routing - Addressing | 8/1/2016 | | 8/1/2016 | | PASS |
Laura Hunter
|
|
|
With new Subdivision and lot split, the address of facility had to change to 6000 W Denton St
|
Intake Approval | | | 7/29/2016 | | PASS |
|
|
|
|
Intake Approval | | | 5/23/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see mark ups on the check list for outstanding items.
|
Application received | | | 5/16/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 16 2016 4:28PM
|