BLD-Final | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | DONE |
Tony Young
|
|
|
Mitch Phone #: ###-####
|
DOC - Permit Finaled | 12/13/2016 | 12/13/2016 | 12/13/2016 | P | PASS |
Tony Young
|
|
|
provisions made to meet code
|
BLD-Energy code compliance | 8/11/2016 | 8/11/2016 | 8/11/2016 | P | PASS |
Tony Young
|
|
|
Mitch Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2016 | 8/4/2016 | 8/4/2016 | A | PART |
Tony Young
|
|
|
Mitch Phone #: ###-####,, need to block between upper roof area I joists,, need to verify seal pack,, no windows in at this point,,, ok to insulate
|
BLD-Wall Bracing | 7/29/2016 | 7/29/2016 | 7/29/2016 | P | PASS |
Jim Sly
|
|
|
Mitch Phone #: ###-####
|
BLD-Foundation | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | DONE |
Tony Young
|
|
|
Andy Phone #: ###-####
|
BLD-Footing | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | DONE |
Tony Young
|
|
|
|
BLD-Footing | 5/27/2016 | 5/31/2016 | 6/1/2016 | A | PASS |
Jim Sly
|
|
|
Andy Phone #: ###-####
|
PubWorks Subgrade Approval | 6/1/2016 | 6/1/2016 | 6/1/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 5/24/2016 | | |
|
|
|
|
Routing Walk-In (BLD) | 5/24/2016 | 5/24/2016 | 5/24/2016 | P | PASS |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 5/24/2016 | | 5/24/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Plan assigned to (LEG) Tisha | 5/24/2016 | | 5/24/2016 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 5/24/2016 | | 5/24/2016 | | PASS |
Evan Jenkins
|
|
|
waiver request approved per attached conditions
|
1st review completed | | | 5/24/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 5/24/2016 | | 5/24/2016 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2016 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/24/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/24/2016 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 5/17/2016 | 5/17/2016 | 5/17/2016 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 5/17/2016 | 5/17/2016 | 5/17/2016 | A | FAIL |
David Ferguson
|
|
|
Hillside property - need engineering for foundationa and Jason T. to sign-off on geotech comments.
|
Application received | | 5/17/2016 | | | |
|
|
|
|