BLD-Final | 7/17/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 7/18/2017 | | DONE |
|
|
|
|
BLD-Final | 7/14/2017 | 7/17/2017 | 7/17/2017 | A | CANC |
Jim Sly
|
|
|
Colby Phone #: ###-#### need zoning
|
Zoning Approval | 7/17/2017 | 7/17/2017 | 7/17/2017 | | DONE |
Todd Tucker
|
|
|
|
PubWorks Occupancy Approval | 7/14/2017 | 7/14/2017 | 7/14/2017 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 7/10/2017 | 7/11/2017 | 7/11/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | FAIL |
Troy Cobbley
|
|
|
Provide verification of evacution guides as discussed, provide closers on exterior doors, provide 3' minimum clearance from smoke alarms to bathroom doors with tub or shower.
|
BLD-Energy code compliance | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | PASS |
Jim Sly
|
|
|
south end; Colby Phone #: ###-####
|
BLD-Energy code compliance | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | PART |
Jim Sly
|
|
|
Colby Phone #: ###-#### N 1/2 f
|
BLD-Framing/Rough-in | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-####
|
BLD-Other | 3/14/2017 | 3/15/2017 | 3/15/2017 | A | PASS |
Jim Sly
|
|
|
fire caulking; Colby Phone #: ###-####
|
BLD-Framing/Rough-in | 3/14/2017 | 3/15/2017 | 3/15/2017 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-####
|
BLD-Wall Bracing | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PASS |
Jim Sly
|
|
|
Shear // Colby Phone #: ###-####
|
BLD-Wall Bracing | 2/15/2017 | 2/16/2017 | 2/16/2017 | P | PART |
Jim Sly
|
|
|
partial shear on breezeways-Colby Phone #: ###-#### Breezways only.....OK.
|
BLD-Foundation | 11/15/2016 | 11/16/2016 | 11/16/2016 | A | PASS |
Jim Sly
|
|
|
Rebar // Colby Phone #: ###-####
|
BLD-Footing | 11/15/2016 | 11/16/2016 | 11/16/2016 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-####
|
BLD-Foundation | 11/7/2016 | 11/8/2016 | 11/8/2016 | P | CANC |
Jim Sly
|
|
|
Colby Phone #: ###-#### Ridgid insulation at foundation....OK.
|
BLD-Foundation | 11/3/2016 | 11/4/2016 | 11/7/2016 | P | PASS |
Dave Hannah
|
|
|
Dane Phone #: ###-####
|
OVERRIDE | | | 11/7/2016 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/7/2016 | | DONE |
|
|
|
Plan Mod
|
(F) Reprint permit | | | 11/7/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2016 | | DONE |
|
|
|
DO NOT RE ISSUE PLAN MOD
|
Plan assigned to (CDM) | 10/21/2016 | 10/21/2016 | 11/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/27/2016 | | 11/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2016 | | DONE |
|
|
|
|
BLD-Footing | 11/2/2016 | 11/3/2016 | 11/3/2016 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Routing - MECHANICAL | 10/27/2016 | | 10/28/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/27/2016 | | 10/28/2016 | | PASS |
Cody Riddle
|
|
|
|
Plan Modification Accepted | | | 10/21/2016 | | DONE |
Christina Prado
|
|
|
Plan mod to update mechanical HVAC from roof mounted to wall mount units
|
Print Occupancy Form | | | 10/13/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/13/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 10/6/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 8/12/2016 | 8/12/2016 | 10/6/2016 | | PASS |
Carl D Madsen
|
|
|
first review completed
|
Routing - PLAN CHECK | 10/6/2016 | | 10/6/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 10/6/2016 | | 10/6/2016 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/6/2016 | | DONE |
|
|
|
Needs: GC Form, Revised Cert of Value, ACHD
|
Routing - PLAN CHECK | 9/20/2016 | | 9/24/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 9/20/2016 | | 9/22/2016 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 9/21/2016 | | 9/21/2016 | | PASS |
Bill VanDegrift
|
|
|
water heaters resized ok, should have had a typical piping plan
|
Routing Off Site - STRUCTURAL | 9/20/2016 | | 9/20/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/1/2016 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/12/2016 | | 9/1/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING Land Div | 8/12/2016 | | 8/18/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLANNING | 8/17/2016 | | 8/17/2016 | | PASS |
Cody Riddle
|
|
|
Site inspection confirmed the landscaping along Cloverdale Road was installed with the subdivision.
|
Routing PW Drainage | 8/12/2016 | | 8/17/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 8/12/2016 | | 8/16/2016 | | FAIL |
Bill VanDegrift
|
|
|
Water heaters spec'd for job doesn't meet 1st hour rating requirements of ISPC.
|
Routing - FIRE | 8/12/2016 | 8/12/2016 | 8/15/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Erosion and Sediment | 8/12/2016 | | 8/15/2016 | | PASS |
Evan Jenkins
|
|
|
(Site prep inspection and approval required prior to earth disturbance)
(DROPZONE APARTMENTS) 32 unit apartment project, (4) 2 story, 8 unit apartment buildings.
|
Routing PW Sewer Design | 8/12/2016 | | 8/15/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Solid Waste | 8/12/2016 | | 8/15/2016 | | PASS |
Peter J. McCullough
|
|
|
Approved for 3-yard container only.
|
Routing - PLANNING | 8/12/2016 | | 8/15/2016 | | FAIL |
Cody Riddle
|
|
|
A number of plantings between the buildings and Cloverdale Road have not been included. Emailed applicant today. CER 8/15/16
|
Routing - Addressing | 8/12/2016 | | 8/15/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - MECHANICAL | 8/12/2016 | | 8/15/2016 | | FAIL |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 8/12/2016 | | 8/12/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 8/12/2016 | | PASS |
|
|
|
|
Intake Approval | | | 5/23/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see mark ups on check list for outstanding items.
|
Application received | | | 5/20/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2016 9:35AM
|