Permit Information
Permit NumberBLD16-01892
StatusFinaled
Name Ted Buck
Site Address 8650 W FAIRVIEW AVE
Project NameCentral Assembly Church
Customer Number 
ePlanReviewYes
Description
(CENTRAL ASSEMBLY - CITY HOPE CHURCH) Permit for new owner and new additioal school use. Minor remodeling for platform expansion with existing lift for accessible route, play yard with fence/gates, handrails and guard modifications per approved plans to meet current code requirements. An area of safe dispersal will be installed under this permit. The A3 occupancy for the church is remaining. The school use "E" will be added to the existing A3 occupancy. See letter from church dated 6/22/16 and plan review report for limited use and occupany of this building. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 12/22/20171/11/2018 DONE
Mailed 1-12-18
First Notice 11/27/201712/12/2017 DONE
Mailed 12-13-17
BLD-Final11/17/201711/17/201711/17/2017PPASS
DetailsJim Sly
Ted 208 440 6227
OK for Perm Occ.
BLD-Final11/17/201711/17/201711/17/2017ACANC
DetailsJim Sly
BLD-Final11/16/201711/17/201711/17/2017ACANC
DetailsJim Sly
FIRE-Final Inspection11/16/201711/17/201711/17/2017APASS
DetailsJim Page
No fire sprinkler modifications (fire sprinkler inspection is currrent), no fire alarm modifications (refer to attached letter in documents: BO & FM OCC LOAD REQUEST for occupancy reduction for voice evacuation on the fire alarm system) fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
BLD-Final11/16/201711/16/201711/17/2017PCANC
DetailsJim Sly
Ted Buck Phone #: ###-####
Print Occupancy Form  11/17/2017 DONE
Permanent Occupancy  11/17/2017 DONE
BLD-Final8/28/20178/28/20178/28/2017PNR
DetailsJim Sly
Call half hour before // Ted Phone #: ###-####
BLD-Other7/14/20177/14/20177/14/2017PPART
DetailsJim Sly
for lift-call 30 mins ahead for access-Ted Phone #: ###-####
BLD-Conference10/10/201610/10/201610/10/2016PDONE
DetailsJim Sly
Ted Phone #: ###-####
Looked at Framing in hallway at new door. Framing ......OK.
(F) Reprint permit  10/10/2016 DONE
Issue PAID IN FULL permit  7/21/2016 DONE
Print Occupancy Form  7/21/2016 DONE
Routing - FIRE7/12/20167/12/20167/12/2016 PASS
DetailsKatie Marron
Revised report for approved reduced occupancy load.
Plan assigned to (AJS)6/8/20166/8/20167/12/2016 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed 6/15 Level 3 TI - ePlanReview - Central Assembly Church
PLANS/APPL TAKEN TO FRONT DESK  7/12/2016 DONE
Permit Ready to Issue  7/12/2016 DONE
****NEED GC form and certificate of value/// 7-15-16 Requirements met- KRS
Routing - PLAN CHECK7/8/2016 7/12/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLANNING7/8/2016 7/8/2016 PASS
DetailsTed Vanegas
Maximum occupancy is 465 based on available parking (155 spaces.
Routing - PLAN CHECK6/16/2016 6/20/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE6/16/20166/16/20166/16/2016 PASS
DetailsKatie Marron
Revised report attached to case.
Route to Impact Fee Review6/10/20166/13/20166/16/2016 PASS
DetailsCindy M. Gould
Plan Reviewer's activity  6/16/2016 DONE
DetailsAdele J Schaffeld-Griffin
sent drawings back to have sheets named to version, spoke with Mike
1st review completed  6/10/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK5/27/2016 6/10/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Plan Reviewer's activity  6/9/2016 DONE
DetailsAdele J Schaffeld-Griffin
I spoke with planning (TED) in regards to the drawings stating child care facility and the CUP not refrencing anything about child care. He said he approved the drawings with the child care and his CUP was for the school.
Plan assigned to (JG)5/27/20165/27/20166/8/2016 DEFR
DetailsJavier Guzman
6/15 Level 3 TI - ePlanReview - Central Assembly Church
Routing PW Solid Waste5/27/2016 6/8/2016 PASS
DetailsPeter J. McCullough
Passed in ePlan review by Peter McCullough
Routing - FIRE5/27/20165/27/20166/3/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect
Routing - PLANNING5/27/2016 6/1/2016 PASS
DetailsTed Vanegas
Ted Vanegas - CUP15-00104
Routing - Addressing5/27/2016 5/27/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS5/27/2016 5/27/2016 PASS
DetailsRachael Beierle
Pending Assignment by JCB5/27/2016 5/27/2016 DONE
DetailsJason Blais
Routing PW Street Lights5/27/2016 5/27/2016 PASS
DetailsTom Marshall
Routing PW Drainage5/27/2016 5/27/2016 PASS
DetailsBrian Murphy
Intake Approval  5/26/2016 PASS
DetailsJason Blais
Prescreen approved by Tim Woodard and plan review fees paid.
Application received  5/24/2016 DONE
Application submitted via PDS Online on May 24 2016 2:33PM