Permanent Occupancy | | | 6/8/2016 | | DONE |
|
|
|
|
BLD-Final | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/1/2016 | 6/2/2016 | 6/2/2016 | P | FAIL |
Jim Storey
|
|
|
Justin or Mark ###-####-pleae call 30 minutes prior for access Phone #: ###-#### glazzing not rated in rated door
|
FIRE-Final Inspection | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher is in place with current inspection tag. Final life fire safety inspection passed/complete.
|
Plan assigned to (CJW) | 5/26/2016 | 5/26/2016 | 6/1/2016 | | PASS |
Carl Westfall
|
|
|
(May 30 - 3 days)
|
Routing - PLAN CHECK | 5/26/2016 | | 6/1/2016 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 6/1/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2016 | | DONE |
|
|
|
all requirements met
|
Print Occupancy Form | | | 6/1/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2016 | | DONE |
|
|
|
called Eric- left message with Rosanna that permit is ready
|
Issue PAID IN FULL permit | | | 6/1/2016 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/26/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/26/2016 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/26/2016 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 6/18/2016 | | | |
|
|
|
|
Application received | | 5/26/2016 | | | |
|
|
|
|