BLD-Final | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Jim Sly
|
|
|
Garage code 6776 enter Phone #: ###-#### Inspection requested via web by Matthew Eberhard
|
DOC - Permit Finaled | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 9/7/2016 | 9/8/2016 | 9/8/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Dan Clark
|
BLD-Framing/Rough-in | 8/25/2016 | 8/26/2016 | 8/26/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew Eberhard
|
BLD-Wall Bracing | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Dan Clark
|
Plan Modification Accepted | | | 8/2/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/2/2016 | | 8/2/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 6/29/2016 | 6/30/2016 | 7/1/2016 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/29/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/28/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 6/1/2016 | 6/1/2016 | 6/28/2016 | | DONE |
Brian McGowan
|
|
|
due 6/10 - Failed - wall bracing and misc.
|
Routing - PLAN CHECK | 6/28/2016 | | 6/28/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/28/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
1st review completed | | | 6/9/2016 | | FAIL |
Brian McGowan
|
|
|
Need to verify Wall Bracing
|
Routing - PLAN CHECK | 5/27/2016 | | 6/9/2016 | | FAIL |
Brian McGowan
|
|
|
Need to verify Wall Bracing
|
Plan assigned to (LEG) Tisha | 5/27/2016 | | 6/1/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 6/1/2016 | | 6/1/2016 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 5/27/2016 | | 5/31/2016 | | FAIL |
Troy James
|
|
|
emailed correction to western heating
|
Application received | | | 5/27/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 27 2016 12:29PM
|
Plans ACCEPTED BY PLAN TECH | | | 5/27/2016 | | DONE |
|
|
|
|
Intake Approval | | | 5/27/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/27/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 5/27/2016 | | 5/27/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 5/27/2016 | | 5/27/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/27/2016 | | 5/27/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLAN CHECK | 6/20/2016 | | | | FAIL |
Brian McGowan
|
|
|
Wall Bracing does not meet SR-102 requirements
|